To main content

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

The first phase of Maasvlakte 2 comprises an industrial site area measuring 700 hectares. The port basins are dredged to –20 m NAP (Normal Amsterdam Water Level), so that even the largest (next generation) container vessels can dock. An important component of the project is the construction of the overall sea defenses. The outer contour bordering the sea is about 11 kilometers long, and includes a hard (rocks) and a soft (dunes) section. The 3.5 km hard section requires 20,000 concrete blocks, each weighing approximately 40,000 kg and 7 million tons of broken rock, of which 1.5 million tons is recycled from the existing sea defenses, from Maasvlakte 1, and 5.5 million tons is imported from quarries in North-West Europe (mainly from Norway). PUMA is also managing the construction of the quaywalls, railways and roads for the Maasvlakte 2 project. About 140,000 tons of asphalt, 110.000 tons of mixed aggregate and 112,000 m2 of sandcement stabilisation will be used for the construction of the roads.

'We are pleased and proud as a Dutch company to be involved in this major project in our own country. The Second Maasvlakte confirms the position of the Netherlands as a leading nation in maritime construction.' Peter Berdowski
Boskalis CEO

Conclusion

The construction of Maasvlakte 2 is one of the most high-profile projects in the history of hydraulic engineering. The complexity and the enormous dimensions of the project are unrivalled. The project is carried out according to the highest quality and safety standards, resulting in the lowest Lost Time Injury Frequency (LTIF) figures ever achieved in The Netherlands. PUMA will remain responsible for the maintenance of the sea defense for another five years after the project completion in 2013. The Maasvlakte 2 area will ultimately encompass a total of 1,000 ha (nett) of industrial complex located directly on deep and navigable water.

Related projects

Selected filters
Oman_-_the_Wave_I_header.jpg

Reclamation, dredging and excavation, The Wave

Through Orascom, the Omani government is developing their tourist and real estate sector in order to diversify its economical drivers. The Wave, Muscat is the first freehold tourism and residential development to be launched in the Sultanate of Oman. The USD 805 million project will stretch along 7 kilometers (4.35 miles) of beachfront land overlooking the Gulf of Oman and covers an area of approximately 2.5 million square meters (26.9 million square feet). It is located in Muscat, Oman's capital city, about 5 kilometers (3.1 miles) from Muscat’s Seeb International Airport.

f__Queen_of_the_Netherlands_def_header.jpg

Land reclamation and revetments works, Salam Yiti

Salam Yiti is located near the south of Muscat, about 40 minutes away from Muscat’s international airport, and minutes from the traditional business and hotel district of Qurum. The Salam Yiti development covers 420 hectares of land and climbs as high as 140 meters above sea level. The project is being developed at a cost of USD 1.7 billion. It was scheduled for completion by 2013. The development plan features luxury hotels, state-of-the-art spas, exclusive villas and apartments, and luxury townhouses set on the beach and in the mountains and select shopping and dining outlets, all surrounded by a championship golf course, marina, a wellness and eco-marine center.

angola_2_header.jpg

Dredging, reclamation and
shore protection, Soyo LNG

Angola is one of the world’s deep water oil exploration ‘hot spots’. More than 50 significant oil discoveries in Blocks 14, 15, 17 and 18 are believed to contain at least 10 billion barrels of oil. With the increase in oil production comes large quantities of associated gas. Historically, in the absence of a local market, associated gas has been flared or reinjected into the reservoirs. Sonangol, the state oil company, and some of its oil producing partners developed the Angola LNG Project to reduce flaring of gas and curtail gas injection. Angola LNG is a joint venture project involving the major oil producers in the country. Sonangol and Chevron are the co-leaders of the project; the other partners are Total, ENI and BP.

MBK2-2_header.jpg

Port expansion, Ras Laffan

The Ras Laffan project is one of the largest maritime engineering projects in the world. Its sheer size can best be viewed from space. Over a period of three years, more than 3,000 specialists have been working together to create the largest LNG harbor in the world. The total contract value is approximately USD 2 billion, with the Boskalis share amounting to 50%. Qatar has natural gas reserves of roughly 25 trillion m3, 15% of the world total. The gas is transported from the Offshore North Field (26,000 billion m3), 80 kilometers north of Qatar, into Ras Laffan, where it is liquefied and pumped into latest generation tankers.

Boskalis_Aerials_by_Lucas_Dawson__15__header.jpg

Channel deepening, Melbourne

To maintain its position as number one container and general cargo port in Australia, the Port of Melbourne Corporation (PoMC) proposed a plan to make the port accessible to 14m draught vessels during all tidal phases. Following the selection of a partner in April 2004 an Alliance Agreement was developed between PoMC and Boskalis Australia Pty Ltd, i.e, a contract where risk sharing was the norm and Boskalis could provide advice during the project development phase using its ‘in house’ expertise and experience.

klein_1_header.jpg

Gas fields development, Krishna Godavari basin

A large-scale dredging, trenching, pipe pulling and backfilling project. Reliance Industries develops the offshore gas field known as Block KGDWN-98/3 in the Krishna Godavari Basin, Bay of Bengal off the East Coast of India. The gas field will be linked to onshore customers and covers an area of approximately 7,500 km2. The field stretches an area 40 to 60 kilometers southeast of Kakinada. The scope of works comprised the dredging of a 21 kilometers long and 18 meters wide trench for three 24" gas pipelines, each with a 6" piggyback pipeline, one 12" effluent pipeline and two umbilical cables in water depths ranging from 0 to 50 meters. After pipe laying by the main contractor the pipeline trench was backfilled with partly rock and sand.