Rock installation, PDET

In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

The pipeline network total extension of 25 km consists of three Pipeline End Manifolds (PLEM) installed on the seabed at a depth of approximately 100 m. The terminal, constructed to comply with the Oil Outflow and Handling Master Plan of Campos Basin – PDET, was the solution for the oil outflow produced at platforms P51, P53, P55 and Roncador module. Petrobras pro-actively initiated this project to ensure the future integrity and safety of the oil production facilities. Petrobras considered specialized accurate rock installation techniques to protect, stabilize and isolate the pipelines and subsea structures and in doing so to protect the environment. For Petrobras, Boskalis and partners it was the first time an IBAMA (Environmental) licensed rock installation project was carried out in Brazil. IBAMA issued this license after a detailed analysis of amongst others the impact on the environment and the proposed measures to mitigate turbidity during the installation process. Also the IBAMA guidelines with regard to the selection of the quarry mining, production of the rock, logistics and actual loading of the vessel, were fully met.

Quality and safety performance

The safety performance on the project was excellent. Before mobilization several safety and quality pre-inspections were carried out by independent auditors and Petrobras representatives; all findings and observations were resolved before arrival in Brazil to guarantee a smooth importation process. During the project preparation phase the Boskalis NINA (No Injuries No Accidents) program was implemented; all truck drivers and other personnel were successfully trained and explained the values and rules of the safety program. Special attention was paid to safe driving, the Boskalis Offshore theme for the year 2011. Thanks to the thorough preparations almost 400,000 accident-free km were driven on the project.

Related projects

Selected filters
Fleet_OE_Moho.jpg

Transport and installation Moho Nord FPU

For the Total Moho Nord FPU project, Dockwise has transported the newbuild FPU Likouf from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Port-Gentil, Gabon. It was a world-record cargo load onboard a semi-submersible vessel to date. 

Thien_Ung_I.jpg

Installation topside
and living quarters,
Thien Ung BK-TNG

For the Vietsovpetro Thien Ung project, Boskalis has installed the Thien Ung BK-TNG 4,200 metric tonne (mt) topside and 850 mt living quarter by offshore heavy lifting with the sheerleg Asian Hercules III. It was the world’s heaviest lift installation of a topside by a sheerleg in an offshore environment to date. 

1407-0505-30_header.jpg

Development gas export pipeline, Ichthys

The Ichthys development revolves around the construction of a new 42-inch deep sea natural gas pipeline from the Ichthys field in the Browse Basin 880 kilometers to Darwin onshore. The pipeline will run through the Darwin harbor, requiring dredging services in the near shore area, rock installation and the construction of a landfall. Owner INPEX Operations Australia Pty Ltd is developing LNG process facilities on Blaydin Point near Darwin, Northern Territory of Australia.

140718_-_48.jpg

Wintershall RAVN and A6-A

Wintershall Noordzee B.V. installed a new remote platform RAVN as a crude production tie-back to A6-A. RAVN is a remote and unmanned crude well unit. Utilising a dry-tree design, all control, power and metered injection for the well will be via the 18.2-km control umbilical between the new satellite platform RAVN in the Danish sector and the operational platform A6-A in the German sector.

AT2C5860_header.jpg

Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

ZP_-_pic4_header.jpg

Mooring replacement phase 2, Zafiro Producer

Mobil Equatorial Guinea Incorporated, an affiliate of ExxonMobil, entered into a contract with Boskalis for the Zafiro Producer Mooring Replacement Project Phase 2. The Zafiro Producer is installed in 180 m (590 ft)water depth approximately 74 km (40 nauticalmiles) west of Malabo, Equatorial Guinea.