In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

The pipeline network total extension of 25 km consists of three Pipeline End Manifolds (PLEM) installed on the seabed at a depth of approximately 100 m. The terminal, constructed to comply with the Oil Outflow and Handling Master Plan of Campos Basin – PDET, was the solution for the oil outflow produced at platforms P51, P53, P55 and Roncador module. Petrobras pro-actively initiated this project to ensure the future integrity and safety of the oil production facilities. Petrobras considered specialized accurate rock installation techniques to protect, stabilize and isolate the pipelines and subsea structures and in doing so to protect the environment. For Petrobras, Boskalis and partners it was the first time an IBAMA (Environmental) licensed rock installation project was carried out in Brazil. IBAMA issued this license after a detailed analysis of amongst others the impact on the environment and the proposed measures to mitigate turbidity during the installation process. Also the IBAMA guidelines with regard to the selection of the quarry mining, production of the rock, logistics and actual loading of the vessel, were fully met.

Quality and safety performance

The safety performance on the project was excellent. Before mobilization several safety and quality pre-inspections were carried out by independent auditors and Petrobras representatives; all findings and observations were resolved before arrival in Brazil to guarantee a smooth importation process. During the project preparation phase the Boskalis NINA (No Injuries No Accidents) program was implemented; all truck drivers and other personnel were successfully trained and explained the values and rules of the safety program. Special attention was paid to safe driving, the Boskalis Offshore theme for the year 2011. Thanks to the thorough preparations almost 400,000 accident-free km were driven on the project.

Related projects

Selected filters
TSHD_Queen_of_the_Netherlands_dredging_hard_spot_close_to_the_existing_SPM_header.jpg

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

131007_1_Sunset_in_the_field_header.jpg

Mooring installation and hook-up, OSX3

OGX - OSX is a Brazilian oil and gas company owning and operating several floating facilities in Brazil. MODEC secured the FPSO purchase contract and subsequently awarded Boskalis the Mooring Installation & Hook-up contract. The FPSO had to be installed in the Tubarão Martelo Field, located in the Campos Basin, Brazil, in 105 meters water depth.

IMG_0814_header.jpg

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

NWS_Barge_near_completion_header.jpg

Refurbishment water station, Olero Creek

In November 2010 Chevron Nigeria Limited (CNL) awarded the contract to refurbish this facility to Saipem Contracting Nigeria Limited (SCNL) with Nigerian Westminster Dredging and Marine Limited (NWDM) as subcontractor. The Olero Creek Restoration Project (OCR) is a 70 million US$ construction and commissioning subcontract. The scope of work is the refurbishment and reinstatement of the North Water Station (NWS) and its hook up to the interconnecting piping at Olero Creek.

Provision and installation of submarine fiber optic cable, Strait of Magellan

In September 2011 Boskalis was awarded a contract worth approximately EUR 30 million to provide and install a submarine fiber optic cable across the Strait of Magellan, Argentina. The contract was awarded by the state-owned corporation AR-SAT (Empresa Argentina de Soluciones Satelitales S.A.).

PAG_9_TRANSPORT_FLEET_SUPPORTS_LINCS_WINDFARM_CONSTRUCTION_-_Groot_header.jpg

Offshore wind farm, LINCS

SMIT Transport is transporting the wind turbine foundations for the new Lincs Offshore Windfarm, situated off Great Yarmouth, UK. When completed, the windfarm will consist of 75 turbines capable of generating sufficient power to meet the annual demand of some 200,000 households.