To main content

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

The SBM is connected to the shore by a 48” concrete weight coated submarine pipeline. To extend the operating life of this pipeline, a 2.7-km section starting at the Pipeline End Manifold (PLEM) containing most of the corroded spots was replaced. The overall project scope included laying approximately 2.7 kilometers of new pipeline in the re-routed trenched corridor, de-oiling the existing pipeline, removing the existing SBM buoy and PLEM, in-situ inspection of the SBM mooring chains, de-burial, cutting and removal of the existing pipeline at both tie-in locations, installation of the new PLEM, associated tie-in connections between the newly laid pipeline and the existing facilities, re-installation of the SBM, hydro-testing and final leak testing of the modified facilities. The scope was extended to include the removal of the replaced pipeline section. Due to the close proximity to the existing SBM and its mooring chains, soil surveys requiring anchored vessels could not be carried out on a potential hard spot. There was a serious concern that dredging this section would not be possible using the proposed dredging equipment during pipeline outage. Boskalis suggested dredging this particular trench section using the Trailing Suction Hopper Dredger (TSHD) Queen of the Netherlands with a ripper draghead well in advance of the actual trench dredging works. The ripper draghead broke and removed the weathered rock and overlying, stiff to very stiff, clay and gravel.

Related projects

Selected filters

Gas pipeline project, Trans Thailand Malaysia

The Trans Thailand Malaysia Gas Pipeline Project comprised the installation of a 34 inch concrete coated gas pipeline, running from the joint Thai-Malaysia development area approximately 270 kilometers offshore towards the southern Thai coast near Chana. As part of this project a contract was awarded to the Boskalis Offshore B.V. - Tideway B.V. consortium for the provision of the dredging and backfilling works, whereas Boskalis Offshore provided the main equipment and project support.

Seahorse_04_header.jpg

Glory hole excavation, White Rose

The White Rose offshore oil field is the third major oil field in the Jeanne d’Arc Basin on the Grand Banks, some 350 kilometers east of St. John’s, Newfoundland, Canada and within 50 kilometers from the Terra Nova and Hibernia fields. The South White Rose oil pool covers approximately 40 square kilometers and contains an estimated 200-250 million barrels of recoverable oil.

Development gas export pipeline,
Hibiscus to Point Fortin

The NCMA Development Project comprised the development of the North Coast Marine Area, which is located in the Caribbean Sea and Bay of Paria, Trinidad. The project included the installation of a 24" Gas Export Pipeline from the Hibiscus Platform to a landfall at Point Fortin. From the landfall the pipeline was routed by directional drilling and by surface laid pipeline, to a termination point in the Atlantic LNG Terminal at Point Fortin. As part of this project Boskalis was awarded the contract for the provision of landfall, directional drilling and onshore pipeline installation and testing of the 24" gas pipeline system.

Sandpiper_foto_offshore_2_header.jpg

Hanze F2a Development Project

Hanze, 200 kilometers offshore Den Helder in block F/2 of the North Sea, is the first operated development in the Dutch sector by Germany's Veba Oil. The oilfield reserved approximate 34 million bbl, plus 40 bcf of associated gas. 

Installation gas pipeline, Takoradi

Late November 1998 Boskalis was awarded a subcontract for the installation of two marine pipelines to supply and discharge cooling seawater for the Takoradi thermal power plant that was under construction for the Volta River Authority, near the village of Aboadze approximately 20 kilometers north-east of Takoradi, Republic of Ghana.

WD_Fairway_and_Sandpiper_near_platform_header.jpg

Re-insulation Gannet 'C' Bundles, North Sea

The Gannet 'C' satellite field, which is located in the North Sea at 112 miles East of Aberdeen in 95-meter water depth, comprises four drill centres, each having one or more producing wells. The drill centres are connected to the local platform Gannet 'A' by four flowline bundles with a total length of 10 kilometers. A glycol-based gel, filling the annulus of the Gannet 'C' carrier pipe, insulated the individual flow lines. Prompted by degradation of the gel and the resulting drop in oil and gas arrival temperatures at the platform, an EPIC project took off for a re-insulation system. The objective of the re-insulation system was that it should provide sufficient insulation to the bundles in order to safeguard production during the total field life of Gannet 'C', being a minimum lifetime of 15 years. Boskalis Offshore was supported by Hydronamic - the in-house engineering department.