Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

The umbilical forms the entire link between the remote platforms, supplying and controlling all functions and ensuring continual feedback and monitoring of L6-B. The umbilical supplies all the necessary input data, control and feedback to eliminate the usual day-to-day requirement of direct human contact. The umbilical was installed from L8-P4 first end to second end pull-in at L6-B remote end. Both platforms are located in Dutch territorial waters in the North Sea. The umbilical was connected/pulled in to L6-B via a J-tube and internal conductor to the L6-B topside - TUTA. The umbilical will be installed from L8-P4 - first end with pull-in to topside deck via a J-tube, laid in corridor separate from the 8-inch pipeline between L8-P4 and L6-B.

FACTS AND FIGURES

  • Water depth 30-35 meters
  • Challenging North sea conditions.
  • Challenging soft seabed.
  • Fast-track project, with a short lead-time between award and installation – Feb 2014, July/Aug installed.
  • Stepped phase process of pull-in, laying and burial ops.
  • Completed on time, with no incidents.
  • Umbilical loaded quickly and safely.
  • Umbilical length 19.5 km.
  • Burial scope of single pass burial of umbilical minimum requirement of 1m TOC (top of cover).

SCOPE OF WORK

  • Prepare project planning for Boskalis’ scope of work.
  • Survey work, including a pre-burial, as-laid and post-burial survey.
  • Perform route engineering and installation engineering to optimize the performance of the installation scope, including a detailed burial assessment study (BAS).
  • Prepare platform on L8-P4 and L6-B.
  • Define umbilical length together with the client.
  • Umbilical load-out at DUCO Newcastle (UK) onto the installation vessel Ndurance.
  • Hang-off of umbilical end.
  • Crossing 36-inch live gas pipeline Callantsoog.
  • Pull-in at L6-B & L8-P4 platforms – direct from vessel as part of SIM-OPS.
  • Mobilize and demobilize all installation spreads for Boskalis’ scope.
  • Provide engineering support during the offshore umbilical installation, including burial.
  • Provide QHSE management for Boskalis’ scope.

Related projects

Selected filters
Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.

quarry.jpg

Pipeline survey and freespan correction, Bach Ho

The Bach Ho Gas Pipeline is located at the South Coast of Vietnam in the province of Vung Tau and comprises a 16" pipeline installed in 1994. The 16" pipeline is one of the main production lines of Petrovietnam Gas Company (PVGAS) and important for the supply of natural gas to electrical power plants, production and export of LPG and other domestic users.

Gas pipeline project, Trans Thailand Malaysia

The Trans Thailand Malaysia Gas Pipeline Project comprised the installation of a 34 inch concrete coated gas pipeline, running from the joint Thai-Malaysia development area approximately 270 kilometers offshore towards the southern Thai coast near Chana. As part of this project a contract was awarded to the Boskalis Offshore B.V. - Tideway B.V. consortium for the provision of the dredging and backfilling works, whereas Boskalis Offshore provided the main equipment and project support.

Taurus___BKM100_header.jpg

Shore approach and landfall works, Libyan gas transmission system

West Libya aimed to enhance its position in the supply of continental Europe's energy needs. As the demand for cleaner energy was rising and gas consumption in Italy wasexpected to increase, Libya and Italy found common ground for cooperation. Construction of a 700 million USD gas treatment plant in Mellitah was the centrepiece of this West Libya gas project. The Mellitah plant is supplied with gas from the desert Wafa field, 520 kilometers south-west of Tripoli, and from the offshore Bahr Essalam field, 110 kilometers north of Tripoli.

Seahorse_04_header.jpg

Glory hole excavation, White Rose

The White Rose offshore oil field is the third major oil field in the Jeanne d’Arc Basin on the Grand Banks, some 350 kilometers east of St. John’s, Newfoundland, Canada and within 50 kilometers from the Terra Nova and Hibernia fields. The South White Rose oil pool covers approximately 40 square kilometers and contains an estimated 200-250 million barrels of recoverable oil.

Woodside_3_header.jpg

Dredging and backfilling, TSEP

In order to increase the production capacity from the gas condensate fields located off the North West Coast of Western Australia, Woodside Energy Limited, on behalf of the North West Shelf JV Participants, has realized the installation of a multiphase subsea 42" pipeline. The new trunkline supplements an existing 40" pipeline, which conveys gas/condensate from the North West Shelf fields - North Rankin, Goodwyn and Cossack/Wanaea - to onshore treatment facilities located on the Burrup Peninsula near Dampier, Western Australia.