To main content

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Because the Hondsbossche and Pettemer Sea Defense no longer meets safety standards Boskalis is to replenish the coastline using sand. A daring design has been made in which safety is paramount but added value for the environment is also an important aspect: not just safe but also attractive and offering something for everyone. The middle section will provide space for nature while at either end, near the villages of Camperduin and Petten, the focus is on added value for recreation.

The contract

A joint venture of Boskalis Nederland and Van Oord has won a contract from the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin. The client had stipulated 'a safe design using sand with added value for nature and recreation'. Boskalis won the contract on the strength of its unique design ideas. The contract comprises the construction of the new sandy coastline and its maintenance for the next 20 years. The commissioning body for the maintenance part of the contract is the Dutch department of public works. The project, part of the second national Flood Protection Program, involves creating beaches and dunes through sand replenishment.

Work

This weak link in the sea defense will be strengthened using 35 million m3 of sand from the sea, to be supplied by five trailing suction hopper dredgers: three for foreshore replenishment and two for beach replenishment. Coordination between the two large vessels has been arranged in such a way that they can unload simultaneously; the fact that the vessels do not have to wait for one another means lower fuel consumption and therefore lower carbon emissions. Replenishment of the foreshore has been going on since March 2014, with large quantities of sand having been dumped and rainbowed just off the coast. Beach replenishment work started in July and involves pumping the sand for the new beach and dunes through a 1.5 kilometers long underwater pipe. To prevent drifting the new dune will be planted with beach grass and will feature dips in the lee of the wind to allow drift sand to settle on the dune. Conversely, where drifting is desirable we are doing our best to allow for this as well.

Planning schedule

The design was announced in December 2013 and execution of the project started in early 2014. The safety of our coastline must be back up to standard by 31 December 2015. After the sand is in place the joint venture will still be busy in early 2016 realizing cycle tracks, footpaths and bridleways, and creating beach access points as well as several unique features such as the panoramic dune and the beach lagoon. After completion the joint venture of Van Oord and Boskalis Nederland will be responsible for the maintenance for a period of 20 years.

Related projects

Selected filters
Oman_-_the_Wave_I_header.jpg

Reclamation, dredging and excavation, The Wave

Through Orascom, the Omani government is developing their tourist and real estate sector in order to diversify its economical drivers. The Wave, Muscat is the first freehold tourism and residential development to be launched in the Sultanate of Oman. The USD 805 million project will stretch along 7 kilometers (4.35 miles) of beachfront land overlooking the Gulf of Oman and covers an area of approximately 2.5 million square meters (26.9 million square feet). It is located in Muscat, Oman's capital city, about 5 kilometers (3.1 miles) from Muscat’s Seeb International Airport.

f__Queen_of_the_Netherlands_def_header.jpg

Land reclamation and revetments works, Salam Yiti

Salam Yiti is located near the south of Muscat, about 40 minutes away from Muscat’s international airport, and minutes from the traditional business and hotel district of Qurum. The Salam Yiti development covers 420 hectares of land and climbs as high as 140 meters above sea level. The project is being developed at a cost of USD 1.7 billion. It was scheduled for completion by 2013. The development plan features luxury hotels, state-of-the-art spas, exclusive villas and apartments, and luxury townhouses set on the beach and in the mountains and select shopping and dining outlets, all surrounded by a championship golf course, marina, a wellness and eco-marine center.

angola_2_header.jpg

Dredging, reclamation and
shore protection, Soyo LNG

Angola is one of the world’s deep water oil exploration ‘hot spots’. More than 50 significant oil discoveries in Blocks 14, 15, 17 and 18 are believed to contain at least 10 billion barrels of oil. With the increase in oil production comes large quantities of associated gas. Historically, in the absence of a local market, associated gas has been flared or reinjected into the reservoirs. Sonangol, the state oil company, and some of its oil producing partners developed the Angola LNG Project to reduce flaring of gas and curtail gas injection. Angola LNG is a joint venture project involving the major oil producers in the country. Sonangol and Chevron are the co-leaders of the project; the other partners are Total, ENI and BP.

MBK2-2_header.jpg

Port expansion, Ras Laffan

The Ras Laffan project is one of the largest maritime engineering projects in the world. Its sheer size can best be viewed from space. Over a period of three years, more than 3,000 specialists have been working together to create the largest LNG harbor in the world. The total contract value is approximately USD 2 billion, with the Boskalis share amounting to 50%. Qatar has natural gas reserves of roughly 25 trillion m3, 15% of the world total. The gas is transported from the Offshore North Field (26,000 billion m3), 80 kilometers north of Qatar, into Ras Laffan, where it is liquefied and pumped into latest generation tankers.

Boskalis_Aerials_by_Lucas_Dawson__15__header.jpg

Channel deepening, Melbourne

To maintain its position as number one container and general cargo port in Australia, the Port of Melbourne Corporation (PoMC) proposed a plan to make the port accessible to 14m draught vessels during all tidal phases. Following the selection of a partner in April 2004 an Alliance Agreement was developed between PoMC and Boskalis Australia Pty Ltd, i.e, a contract where risk sharing was the norm and Boskalis could provide advice during the project development phase using its ‘in house’ expertise and experience.

klein_1_header.jpg

Gas fields development, Krishna Godavari basin

A large-scale dredging, trenching, pipe pulling and backfilling project. Reliance Industries develops the offshore gas field known as Block KGDWN-98/3 in the Krishna Godavari Basin, Bay of Bengal off the East Coast of India. The gas field will be linked to onshore customers and covers an area of approximately 7,500 km2. The field stretches an area 40 to 60 kilometers southeast of Kakinada. The scope of works comprised the dredging of a 21 kilometers long and 18 meters wide trench for three 24" gas pipelines, each with a 6" piggyback pipeline, one 12" effluent pipeline and two umbilical cables in water depths ranging from 0 to 50 meters. After pipe laying by the main contractor the pipeline trench was backfilled with partly rock and sand.