Coastline fixation, Cotonou

The project was developed to arrest coastline erosion in the densely-populated centre of Cotonou caused by two phenomena: erosion and human interference along the West African coastline.

After Contract award, the first production and installation activities began in June 2012. Construction was completed in July 2014. The project scope encompassed the supply of the materials and the construction of seven groins (EPIs), a revetment with an approximate length of 300 meters, and a breakwater. A total of 2,680 meters of groin, revetment or breakwater have been built and 7.5 kilometers of coastline have been fixated. The materials supplied consisted of:

  • 2,441 concrete Xblocs measuring 4 m3
  • 32,000 m2 of geotextile
  • 530,000 tonnes of rock of miscellaneous categories.

Including concrete aggregates, 545,000 tonnes of raw rock material corresponding to 21,750 truckloads was transported to the site, approximately 3,500 tonnes of cement in 137 twenty-foot containers was transported to the site. The Xbloc elements were produced under our own management using in-house expertise. A concrete laboratory was imported and operated by in-house personnel to ensure close quality monitoring and compliance with the specifications. Boskalis staff supervised the quarry operations. The quarries were located approximately 180 kilometers inland. Boskalis was responsible for loading from the stockpiles in the quarries. The installation spread consisted of one Hitachi 1200, three Caterpillar 385s, three wheelloaders Caterpillar 980, two Caterpillar 365s and four Caterpillar 740 dumpers.

Related projects

Selected filters
8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.

IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.