Dredging and backfilling, TSEP

In order to increase the production capacity from the gas condensate fields located off the North West Coast of Western Australia, Woodside Energy Limited, on behalf of the North West Shelf JV Participants, has realized the installation of a multiphase subsea 42" pipeline. The new trunkline supplements an existing 40" pipeline, which conveys gas/condensate from the North West Shelf fields - North Rankin, Goodwyn and Cossack/Wanaea - to onshore treatment facilities located on the Burrup Peninsula near Dampier, Western Australia.

The trunkline, 135 kilometers long, has been installed by Saipem (Portugal) Comercio Maritimo Sociedade Unipessoal LDA. Boskalis Offshore was subcontracted for the dredging and backfilling works of two trench stretches, in all 25 kilometers long. Work commenced in November 2002 and was completed 11 months later, inclusive of project preparation and interim demobilisation. The 3-meters deep TSEP pipeline trench required the excavation of around 900,000 m3 of material in water depths up to 55 meters. Within three weeks, the works were executed by the Trailing Suction Hopper Dredger Queen of the Netherlands under challenging conditions of offshore working environment, seabed soils, strict technical specifications and the sensitive underwater environment. This demanded thorough preparation of vessel, crew and clear working procedures to guarantee safe, sound and efficient completion of this part of the job. The irregular seabed in combination with the pipe(-lay) characteristics and backfill specifications dictated a narrow pipeline alignment. Four trench transition zones were defined as well. This imposed the need for a detailed dredge plan and round-the-clock survey support, both crucial means to ultimately avoid delays to the dredger. DP/DT, the suction pipe positioning measurement and the dredge process control systems were indispensable features on board.

Related projects

Selected filters
Ineos_IRM_2018.jpg

Ineos IRM 2018

Boskalis Subsea Services was contracted by INEOS E&P A/S for the 2018 Inspection, Repair and Maintenance (IRM) campaign, involving the preparation and execution of 20-off scopes on various assets.

Haven.jpeg

Haven Jack-up upgrade

The Master Marine accommodation unit HAVEN required an upgrade for operations at the Johan Sverdrup Field.

Oman.jpg

DNO Oman block 8 LTD

DNO Oman Block 8 Ltd (DNO) is the operator of the Bukha Field, offshore Khasab, Oman. DNO entered Oman in 2012 and operates the country's only producing offshore fields on behalf of Omani Oil & Gas ministry. Boskalis Subsea Services (BSS) in recent years have assisted DNO with lifting a flare boom onto the WB Platform, making use of a DP2 offshore vessel, also Boskalis provided diving and inspection services to DNO for their SPM Offshore RAK, UAE.

Offshore_energy_heavy_transport_Dockwise_Vanguard_Aasta_Hansteen.jpg

Transport and installation Aasta Hansteen
spar platform

For the Statoil Aasta Hansteen project, Dockwise has transported the newbuild spar hull from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Høylandsbygd, Norway. The spar is the world’s largest spar ever built to date. 

Offshore_windfarm_heavy_transport_installation_wikinger.jpg

Transport and installation turbine foundations offshore wind farm, Wikinger

The Wikinger offshore wind farm has been developed by Iberdrola in the Baltic Sea area, within the German Exclusive Economic Zone (EEZ). The offshore site is about 34 km northeast of the island of Rügen, and covers an area of roughly 50 km², within which 70 wind turbine generators (WTG) of 5 MW and one offshore substation (OSS) are being installed. The water depths for installation range between 36 and 42 meters. When completed the windfarm will deliver 350 MW electrical power to the German national grid. The transport and installation of the 70 WTG foundations and the piles for the OSS has been carried out by Boskalis.

069dd04102016OWF-_c_Kloet.jpg

Offshore wind farm
monopile installation,
Veja Mate

Boskalis is close to completing one of its latest and most significant offshore wind projects - Veja Mate, in the German North Sea. The project involves handling and installing the biggest monopiles in the industry – weighing between 1,230-1,302-tonne a piece – using the biggest pile gripper frame and pile driving hammers in the industry with a brand new vessel, which also happens to be the biggest in the sector. Once complete, the offshore wind farm will produce over 1,6 TWh of green, renewable electricity annually.