To main content

Dredging and backfilling, TSEP

In order to increase the production capacity from the gas condensate fields located off the North West Coast of Western Australia, Woodside Energy Limited, on behalf of the North West Shelf JV Participants, has realized the installation of a multiphase subsea 42" pipeline. The new trunkline supplements an existing 40" pipeline, which conveys gas/condensate from the North West Shelf fields - North Rankin, Goodwyn and Cossack/Wanaea - to onshore treatment facilities located on the Burrup Peninsula near Dampier, Western Australia.

The trunkline, 135 kilometers long, has been installed by Saipem (Portugal) Comercio Maritimo Sociedade Unipessoal LDA. Boskalis Offshore was subcontracted for the dredging and backfilling works of two trench stretches, in all 25 kilometers long. Work commenced in November 2002 and was completed 11 months later, inclusive of project preparation and interim demobilisation. The 3-meters deep TSEP pipeline trench required the excavation of around 900,000 m3 of material in water depths up to 55 meters. Within three weeks, the works were executed by the Trailing Suction Hopper Dredger Queen of the Netherlands under challenging conditions of offshore working environment, seabed soils, strict technical specifications and the sensitive underwater environment. This demanded thorough preparation of vessel, crew and clear working procedures to guarantee safe, sound and efficient completion of this part of the job. The irregular seabed in combination with the pipe(-lay) characteristics and backfill specifications dictated a narrow pipeline alignment. Four trench transition zones were defined as well. This imposed the need for a detailed dredge plan and round-the-clock survey support, both crucial means to ultimately avoid delays to the dredger. DP/DT, the suction pipe positioning measurement and the dredge process control systems were indispensable features on board.

Related projects

Selected filters
Rock_installation_near_wellhead_tower.jpg

Platform installation,
De Ruyter field

The De Ruyter field, discovered in 1996, straddles Blocks P10a and P11b in the North Sea, which are both operated by Petro-Canada. The development consists of a Gravity Base Structure (GBS) with wellhead and lattice towers supporting an Integrated Production Deck (IPD). De Ruyter joins Hanze as Petro-Canada’s second operated offshore field in the Dutch North Sea. Heerema Zwijndrecht was awarded the fabrication, installation and hook-up of the GBS and IPD. The transportation, installation and stabilisation of the GBS was subcontracted to a consortium between Smit Marine Projects and Boskalis Offshore.

HL_Stralsund_header.jpg

Bridge construction, Stralsund

SMIT’s 1,200 tonnes sheerlegs Taklift 7 completed a major German bridge building programme during 2006. The sheerlegs had spent several months at the new Stralsund Bridge, on the German Baltic coast. This suspension bridge links the mainland with the island of Rügen.

Nearshore_excavation_header.jpg

Pipeline construction, Mumbai Highfields to Uran Trunkline

The Mumbai High Fields to Uran Trunkline Project is situated near Mumbai (Bombay) in India. ONGC Ltd (Oil & Natural Gas Corporation) has constructed two new pipeline connections from the Mumbai High Fields to Uran over a total length of 204 kilometers. These new pipelines have been constructed in order to replace the existing Bombay High Fields to Uran Trunkline, which had already completed more than 25 years of successful operation and had surpassed its design life. The new pipelines are a 30" oil pipeline and a 28" gas pipeline.

Backhoe_dredger_Cornelius_trench_dredging_header.jpg

Construction gas pipeline
Beachfield Upstream
Development

The BUD project entailed the construction of a 66 kilometer, 36" gas pipeline, 63 kilometers offshore and 3 kilometers onshore underground to the treatment facilities. The offshore pipeline runs from the east coast at Beachfield (Rustville), Guayaguayare, to the 'Cassia B' platform complex. At the NGC Abyssinia facilities, 3 kilometers off Beachfield, a new sludge catcher has been developed to separate the liquid or condensate from the natural gas. The condensate is separated from water and metered. The station is also designed to control the pressure of gas, as it enters into the land gas transmission system. NGC's existing 30" and 24" gas pipelines have also been diverted to the new Abyssinia sludge catcher.

IMG_2683_header.jpg

Seabed preparations, Changi Outfall

The Public Utilities Board implemented the Deep Tunnel Sewerage System as a long-term solution to meet the needs for sewerage water collection, treatment and disposal to help maintain Singapore’s clean and healthy environment. In phase one of the Deep Tunnel Sewerage System, the Changi Water Reclamation Plant was constructed in the east of Singapore, from which the Changi Outfall was subsequently constructed. Treated effluent from the water treatment plant will flow through outfall pipelines and be discharged through series of diffusers, dispersing the effluent in the seawater. Boskalis International was awarded the contract for the Changi Outfall in 2002 and formed a joint venture with Archirodon to construct the project.

Rion_Antirion_header.jpg

Heavy lift operations, Rion Antirion bridge

The Rion Antirion bridge, a 2.3 km long cable stayed bridge, consisting of 4 pylons from which the bridge deck is suspended. SMIT was involved in two phases of the project. During the construction of the pylons, SMIT carried out the management for the tow-out and positioning. For the installation of the steel components SMIT carried out the heavy lift operations.