Dredging, reclamation,
reconstruction and environmental
monitoring works, Vilufushi

The Republic of the Maldives consists of 1,190 small coral islands grouped into 26 atolls. Only 200 islands are inhabited. On 26 December 2004, a tsunami originating from Indonesian waters struck the Maldives. This natural disaster had major economic, social and environmental consequences. Of the 200 inhabited islands, 13 were totally destroyed and 56 suffered major damage, including the island of Vilufushi in Thaa Atoll. Houses and infrastructure were heavily damaged. All the surviving residents had to be evacuated to the neighboring island of Buruni to the west of Vilufushi. The government of the Maldives decided to reconstruct the entire island and to extend it considerably by landfilling the shallow reef. Boskalis International was appointed for this work.

Several alternatives were studied. The plan that was finally adopted involved dredging coral sand from an area off the northern reef edge of Vilufushi with a medium-sized cutter suction dredger. The sand was then pumped directly into the area to be filled. The reconstruction included:

  • Removal of all debris.
  • Dredging and reclamation of 1 million m3 of coral sand from the reef to increase the surface of, and raise, the island.
  • Construction of a 2000 meter rock revetment around the island as a breakwater to protect against wave penetration.
  • Dredging of a new harbor to 3 meters below sea level.
  • Construction of a 350 meter quay wall using pre-cast concrete elements.
  • Construction of a 350 meter breakwater to protect against wave penetration. 

Monitoring during dredging and reclamation

The Maldives have a very rich marine biodiversity, which requires safeguarding through special measures, in particular during dredging and reclamation activities. A special monitoring program was required to monitor changes in environmental parameters with an adverse impact.

Related projects

Selected filters
8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.

IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.