Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

The early works

In October 2007 Brass LNG awarded Nigerian Westminster Dredging & Marine Limited (NWDM) the Early Works EPC Contract. The project consisted of the construction of a Pioneer Camp and three Pre-Loads to provide early settlement for the future tank farm of the proposed Brass LNG plant. In more detail the Scope of Work consisted of bush clearing and topsoil removal, the construction of temporary roads and pipeline crossings, the excavation of sand for the construction of the pre-loads, installation of vertical drains, the installation of settlement monitoring instrumentation and the monitoring thereof and covering the completed pre-loads with poly sheets.
The Pioneer Camp was designed to be fully self-supporting. Apart from accommodation units it consists of offices, catering, laundry and water treatment facilities. For the power supply three generators were supplied and installed. Furthermore, provisions were made for waste water and sewage treatment and for waste disposal an incinerator was supplied and installed. 

Execution

The bush clearing was mainly sub-contracted to local contractors from the three host communities. Immediately upon having the first areas cleared, sand excavation started to construct the temporary roads, and to create dry and stable platforms for the construction of the accommodation and offices, and for the pre-loads.
Approximately 1,5 million m3 of sand was excavated and transported for the construction of the three pre-loads, which were elevated to  approximately 20 meter height. The required sand was excavated from an onshore borrow area. Over 30 heavy duty dry earth moving machines were brought to site to execute the works, such as excavators, bulldozers, vibro roller compactors, articulated dump trucks, etc.

Related projects

Selected filters
_L4F8705_header.jpg

Port development, Pipavav

As a result of the booming container market in recent years, GPPL and APM Terminals introduced a long term investment plan to further develop the port’s facilities. Phase 2 of the expansion program included the reclamation of a new storage (container stacking) area and the extension of the port’s capacity by deepening the approach, channels and berths, allowing larger (container) vessels to enter the port. Zinkcon Marine Singapore, a subsidiary of Boskalis International B.V., won the contract for the dredging and reclamation works for Phase 2. In the beginning of 2009, however, the client re-evaluated the investment against the background of the dramatic effects of the economic crisis, which seriously affected the global container market. GPPL, APMT and ZMS agreed to optimize the project in such a way that all parties would benefit.

Oman_-_the_Wave_I_header.jpg

Reclamation, dredging and excavation, The Wave

Through Orascom, the Omani government is developing their tourist and real estate sector in order to diversify its economical drivers. The Wave, Muscat is the first freehold tourism and residential development to be launched in the Sultanate of Oman. The USD 805 million project will stretch along 7 kilometers (4.35 miles) of beachfront land overlooking the Gulf of Oman and covers an area of approximately 2.5 million square meters (26.9 million square feet). It is located in Muscat, Oman's capital city, about 5 kilometers (3.1 miles) from Muscat’s Seeb International Airport.

f__Queen_of_the_Netherlands_def_header.jpg

Land reclamation and revetments works, Salam Yiti

Salam Yiti is located near the south of Muscat, about 40 minutes away from Muscat’s international airport, and minutes from the traditional business and hotel district of Qurum. The Salam Yiti development covers 420 hectares of land and climbs as high as 140 meters above sea level. The project is being developed at a cost of USD 1.7 billion. It was scheduled for completion by 2013. The development plan features luxury hotels, state-of-the-art spas, exclusive villas and apartments, and luxury townhouses set on the beach and in the mountains and select shopping and dining outlets, all surrounded by a championship golf course, marina, a wellness and eco-marine center.

angola_2_header.jpg

Dredging, reclamation and
shore protection, Soyo LNG

Angola is one of the world’s deep water oil exploration ‘hot spots’. More than 50 significant oil discoveries in Blocks 14, 15, 17 and 18 are believed to contain at least 10 billion barrels of oil. With the increase in oil production comes large quantities of associated gas. Historically, in the absence of a local market, associated gas has been flared or reinjected into the reservoirs. Sonangol, the state oil company, and some of its oil producing partners developed the Angola LNG Project to reduce flaring of gas and curtail gas injection. Angola LNG is a joint venture project involving the major oil producers in the country. Sonangol and Chevron are the co-leaders of the project; the other partners are Total, ENI and BP.

MBK2-2_header.jpg

Port expansion, Ras Laffan

The Ras Laffan project is one of the largest maritime engineering projects in the world. Its sheer size can best be viewed from space. Over a period of three years, more than 3,000 specialists have been working together to create the largest LNG harbor in the world. The total contract value is approximately USD 2 billion, with the Boskalis share amounting to 50%. Qatar has natural gas reserves of roughly 25 trillion m3, 15% of the world total. The gas is transported from the Offshore North Field (26,000 billion m3), 80 kilometers north of Qatar, into Ras Laffan, where it is liquefied and pumped into latest generation tankers.

Boskalis_Aerials_by_Lucas_Dawson__15__header.jpg

Channel deepening, Melbourne

To maintain its position as number one container and general cargo port in Australia, the Port of Melbourne Corporation (PoMC) proposed a plan to make the port accessible to 14m draught vessels during all tidal phases. Following the selection of a partner in April 2004 an Alliance Agreement was developed between PoMC and Boskalis Australia Pty Ltd, i.e, a contract where risk sharing was the norm and Boskalis could provide advice during the project development phase using its ‘in house’ expertise and experience.