Early works for LNG plant, Brass Island

The Brass LNG Project’s objective is to construct a LNG Complex on Brass Island, Bayelsa State, Nigeria, and in so doing, develop Nigeria’s abundant gas resources, reduce the adverse effect of gas flaring on the environment, and provide social-economic benefits to the local and wider Nigerian communities. The LNG complex will be designed to produce approximately 10 million tons per annum (MTPA) of LNG, as well as LPG and Residual NGL products.

The early works

In October 2007 Brass LNG awarded Nigerian Westminster Dredging & Marine Limited (NWDM) the Early Works EPC Contract. The project consisted of the construction of a Pioneer Camp and three Pre-Loads to provide early settlement for the future tank farm of the proposed Brass LNG plant. In more detail the Scope of Work consisted of bush clearing and topsoil removal, the construction of temporary roads and pipeline crossings, the excavation of sand for the construction of the pre-loads, installation of vertical drains, the installation of settlement monitoring instrumentation and the monitoring thereof and covering the completed pre-loads with poly sheets.
The Pioneer Camp was designed to be fully self-supporting. Apart from accommodation units it consists of offices, catering, laundry and water treatment facilities. For the power supply three generators were supplied and installed. Furthermore, provisions were made for waste water and sewage treatment and for waste disposal an incinerator was supplied and installed. 

Execution

The bush clearing was mainly sub-contracted to local contractors from the three host communities. Immediately upon having the first areas cleared, sand excavation started to construct the temporary roads, and to create dry and stable platforms for the construction of the accommodation and offices, and for the pre-loads.
Approximately 1,5 million m3 of sand was excavated and transported for the construction of the three pre-loads, which were elevated to  approximately 20 meter height. The required sand was excavated from an onshore borrow area. Over 30 heavy duty dry earth moving machines were brought to site to execute the works, such as excavators, bulldozers, vibro roller compactors, articulated dump trucks, etc.

Related projects

Selected filters
hfd_onder_header.jpg

Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

Balboa_2_header.jpg

Port expansion, Balboa

The plans to expand the Panama Canal represent one of the most important infrastructure improvements of the 21st century. Since its opening in 1913 the Canal has provided the shortest and most economically viable shipping route from Pacific to Atlantic seaports. With the ever-increasing size of modern-day vessels, it was inevitable that the Canal would need to be widened and deepened. The expansion of the Canal has made the extension of the Port of Balboa at the mouth of the canal on the Pacific Ocean a necessity. The Phase 4 projects included Marine Works and Civil Works to improve two existing berths and to build a completely new berth capable of handling not only Post Panamax but also Super Post Panamax ships.

DSCF0226_header.jpg

Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

Figure_1_header.jpg

Port environmental mitigation measures, Hamina

Hamina, which is close to the Russian border in south-east Finland, is a home port for the oil industry and a transit harbor for timber, cars and other goods on their way to Russia. To provide access for larger vessels it had to deepen the existing channel by two meters to 12 meters and create a new channel section. Terramare Oy, a subsidiary of Royal Boskalis Westminster, won this assignment in late 2008. The project started in July 2009.

Raahe_1_header.jpg

Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.

_L4F8705_header.jpg

Port development, Pipavav

As a result of the booming container market in recent years, GPPL and APM Terminals introduced a long term investment plan to further develop the port’s facilities. Phase 2 of the expansion program included the reclamation of a new storage (container stacking) area and the extension of the port’s capacity by deepening the approach, channels and berths, allowing larger (container) vessels to enter the port. Zinkcon Marine Singapore, a subsidiary of Boskalis International B.V., won the contract for the dredging and reclamation works for Phase 2. In the beginning of 2009, however, the client re-evaluated the investment against the background of the dramatic effects of the economic crisis, which seriously affected the global container market. GPPL, APMT and ZMS agreed to optimize the project in such a way that all parties would benefit.