To main content

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Scope of work

Boskalis mobilized from Indonesia the TSHD Cornelis Zanen with a hopper capacity of 8,600 m3. The channel was deepened to a minimum depth of 6 m CD over the full width of 100 m. In addition, the approach channel was widened to allow vessels more manoeuvring capabilities when entering the inner port.

Challenges

Tight timeline Dredging operations started immediately on the arrival of Cornelis Zanen, leaving limited time for project preparation. Working in close cooperation with the Myanmar Port Authorities and working with local subcontractors and suppliers, the Boskalis project team finalized the bathymetric riverbed survey measurement campaign within several days of signing the contract. River conditions Navigation from the pilot station 32 km seaward of Elephant Point is generally on the flood tide, and to ensure sufficient depth, crossing both the inner bar and outer bar is timed for high tide. The average tidal range is about 6 m at spring tide and 2.5 m at neap tide. While waves in the Yangon River do not hinder maritime operations, the current velocity of 4 to 6 knots at spring tide has to be controlled. As the channel width of 100 m at Monkey Point is relatively limited, navigation and particularly the dredging operations demanded close attention. Safety and cooperation with other parties The Boskalis No Incident and No Accident (NINA) safety program was implemented and within the short time period available, all parties were informed and were fully compliant with the high safety standard throughout the project. 

Conclusion

Boskalis completed the dredging works in compliance with the contract requirements and in partnership with the Myanmar Port Authority. The works were completed within the budget and the required time frame without accident, incident or spill.

Related projects

Selected filters
FF66817_header.jpg

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Cornelis_Zanen.jpg

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Gabon_Libreville1920.jpg

Port development,
Libreville - Gabon

A new area was constructed in the Port of Libreville for a mineral terminal, dry dock, fishing port, processing facilities and other port activities, such as aggregate processing. This new port development was required to improve and strengthen the logistic capacity for the inland mining industry, to reduce export costs, and thus to increase the competitiveness of mineral exports from Gabon.

Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

IMG_3549_header.jpg

Cleanup sediment treatment, Fox river

As a result of industrialization the riverbed of the Fox River (Wisconsin, USA) had become contaminated with PCBs (polychlorinated biphenyls). Joining together a number of large paper mills based on the banks of the river have established the Fox River Cleanup Group to handle the remediation project. The site is on the federal Superfund program’s National Priorities List.

Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.