Boskalis was subcontracted to install 2 topsides and 3 jackets in the NASR and Umm Shait oil fields: The Accommodation Platform/AP Jacket, the Separation Platform/SP Jacket and the Gas Treatment Platform/GTP Jacket are installed in the NASR Field. The installed net weights of the jackets ranged from 2,270 to 3,070 metric tons.

The floating sheerleg Asian Hercules 3, a 5,000 metric tons heavy lift vessel, was mobilized to Abu Dhabi in 2017 for the jacket installations, thereafter demobilized to NW-Europe for other work and then re-mobilized to Abu Dhabi in 2018 for the topside installations. Asian Hercules 3 and supporting marine spread underwent a strict third-party certification regime to comply with ADMA-OPCO specifications. Project personnel and crew was trained and certified to be able to work in the ADMA OPCO fields. The jackets were fabricated in Shenzhen, China where the lifting rigging for the jackets was preinstalled under Boskalis supervision. The Topsides were fabricated in Ulsan, Korea where the lifting rigging on the topsides was pre-installed under Boskalis supervision. Heavy Transport Vessels were used for the transport of the jackets and topsides to Abu Dhabi. These were equipped with additional mooring winches to enable a safe mooring in the congested NASR and Umm Shaif fields, required for the lift off operations. The Asian Hercules 3 mooring system was modified for the use of Dyneema® mooring ropes, which had to be connected to 75 t piggy backed gravity anchors. The mooring operations and installation lifts went smoothly and provided a quick, safe and successful installation of the 3 jackets and 2 topsides for our customer and end client.

Related projects

Selected filters
Fleet_OE_Moho.jpg

Transport and installation Moho Nord FPU

For the Total Moho Nord FPU project, Dockwise has transported the newbuild FPU Likouf from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Port-Gentil, Gabon. It was a world-record cargo load onboard a semi-submersible vessel to date. 

Thien_Ung_I.jpg

Installation topside
and living quarters,
Thien Ung BK-TNG

For the Vietsovpetro Thien Ung project, Boskalis has installed the Thien Ung BK-TNG 4,200 metric tonne (mt) topside and 850 mt living quarter by offshore heavy lifting with the sheerleg Asian Hercules III. It was the world’s heaviest lift installation of a topside by a sheerleg in an offshore environment to date. 

1407-0505-30_header.jpg

Development gas export pipeline, Ichthys

The Ichthys development revolves around the construction of a new 42-inch deep sea natural gas pipeline from the Ichthys field in the Browse Basin 880 kilometers to Darwin onshore. The pipeline will run through the Darwin harbor, requiring dredging services in the near shore area, rock installation and the construction of a landfall. Owner INPEX Operations Australia Pty Ltd is developing LNG process facilities on Blaydin Point near Darwin, Northern Territory of Australia.

140718_-_48.jpg

Wintershall RAVN and A6-A

Wintershall Noordzee B.V. installed a new remote platform RAVN as a crude production tie-back to A6-A. RAVN is a remote and unmanned crude well unit. Utilising a dry-tree design, all control, power and metered injection for the well will be via the 18.2-km control umbilical between the new satellite platform RAVN in the Danish sector and the operational platform A6-A in the German sector.

AT2C5860_header.jpg

Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

ZP_-_pic4_header.jpg

Mooring replacement phase 2, Zafiro Producer

Mobil Equatorial Guinea Incorporated, an affiliate of ExxonMobil, entered into a contract with Boskalis for the Zafiro Producer Mooring Replacement Project Phase 2. The Zafiro Producer is installed in 180 m (590 ft)water depth approximately 74 km (40 nauticalmiles) west of Malabo, Equatorial Guinea.