Port development, Mombasa

The Port of Mombasa is currently the biggest port on the coast of East Africa north of Durban, and the only international port in Kenya. It is now in the throes of a huge expansion drive to both increase cargo handling capacity and accommodate Panamax and Post Panamax vessels. The port is a transit route for, mainly, Uganda, Rwanda, South Sudan and Northern Tanzania. The current container terminal has an installed capacity of 250,000 TEU but handled more than 770,000 TEU in 2011. The port will raise its profile as a regional hub by building a second container terminal with a capacity of 1.2 million TEU. The port authority decided to construct the container terminal in phases.

Challenges

The main challenge on the project was the fact that Boskalis had to work with weak subsoil with a low bearing capacity. There were also environmental challenges because the sand borrow area was situated between marine reserve parks.

Work method

On 1 August 2012, Boskalis International B.V. signed the sub-contract for the dredging and reclamation works for the first construction phase for the second container terminal. Before construction of the quay walls, three deep trenches were dredged by TSHDs Argonaut and Willem van Oranje to remove the weak subsoil and replace it with sand. Boskalis soil specialists invested large amounts of time and energy in sourcing suitable sand in the immediate vicinity of the project. After the removal of 1 million m3 of soil, the soil improvement area was filled with offshore sand by TSHD Willem van Oranje and a spray pontoon. Reclamation had to take place very carefully to avoid mud slides and circular slip. During reclamation to +1 m CD, the spray pontoon SP10, positioned on six anchors, was used to apply layers of 75 cm; that part of the work was completed successfully on 11 March 2013. The remaining sand was applied in layers up to +5.5 m CD using land pipelines. Boskalis successfully met some challenges with extreme local settlements. The +5,5 m CD level was completed on 7 May 2013. This activity was followed by a surcharge fill to a maximum of +11 m CD to reduce settlement time.

Related projects

Selected filters
Loading_TSHD_by_CSD_header.jpg

Creation bird island, Le Havre port 2000

Le Havre is the fifth largest container port in Europe and is expanding its facilities: the current 14 quays for container vessels are to be expanded with another 12 (all outside the locks). Port 2000’s rationale centres on Le Havre’s determination to position itself as a leading hub.

hfd_onder_header.jpg

Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

Balboa_2_header.jpg

Port expansion, Balboa

The plans to expand the Panama Canal represent one of the most important infrastructure improvements of the 21st century. Since its opening in 1913 the Canal has provided the shortest and most economically viable shipping route from Pacific to Atlantic seaports. With the ever-increasing size of modern-day vessels, it was inevitable that the Canal would need to be widened and deepened. The expansion of the Canal has made the extension of the Port of Balboa at the mouth of the canal on the Pacific Ocean a necessity. The Phase 4 projects included Marine Works and Civil Works to improve two existing berths and to build a completely new berth capable of handling not only Post Panamax but also Super Post Panamax ships.

DSCF0226_header.jpg

Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

Figure_1_header.jpg

Port environmental mitigation measures, Hamina

Hamina, which is close to the Russian border in south-east Finland, is a home port for the oil industry and a transit harbor for timber, cars and other goods on their way to Russia. To provide access for larger vessels it had to deepen the existing channel by two meters to 12 meters and create a new channel section. Terramare Oy, a subsidiary of Royal Boskalis Westminster, won this assignment in late 2008. The project started in July 2009.

Raahe_1_header.jpg

Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.