To main content

Port expansion, Ras Laffan

The Ras Laffan project is one of the largest maritime engineering projects in the world. Its sheer size can best be viewed from space. Over a period of three years, more than 3,000 specialists have been working together to create the largest LNG harbor in the world. The total contract value is approximately USD 2 billion, with the Boskalis share amounting to 50%. Qatar has natural gas reserves of roughly 25 trillion m<sup>3</sup>, 15% of the world total. The gas is transported from the Offshore North Field (26,000 billion m<sup>3</sup>), 80 kilometers north of Qatar, into Ras Laffan, where it is liquefied and pumped into latest generation tankers.

This expansion made it necessary to review the infrastructure of both the petro-chemical installations and the facilities for transportation of the products. The new facilities were to be positioned in a sheltered area. The size of the existing harbor had to be increased from 106 km2 to 246 km2. Upon completion, the harbor has 10 loading facilities.To facilitate LNG berths and many other related activities (cargo, gas-2- liquid products etc.) the following additional works had to be constructed:

  • Facilities for LNG tankers;
  • Liquid-product berthing facilities;
  • Cargo on- & offloading facilities;
  • Vessel repair / dry-dock facilities.

As part of this immense expansion the existing port had to be extended from 8 km2 to 51.2 km2. This project was awarded to Boskalis - Jan de Nul JV.

Project specification

The main activities under the contract were:

  • 24 million m3 dredging of waterways (widening of the existing waterways and additional shelters)
  • 29 million m3 reclamation (areas for tank storage, container handling and future dry docks)
  • The construction of 33 kilometers of breakwaters, for which the following materials were required:

31 million tons of local rock material, 9 million tons of rock from overseas, transported over a distance of 275 n. M., 2.5 million m3 of concrete and 250,000 concrete elements for protection of the structures against wave conditions (Antifers & Accropodes of 3, 4 and 5 m3 each).

Related projects

Selected filters
Muuga_3_header.jpg

Expansion coal terminal, Muuga

The Muuga Coal terminal, sited on a bay, east of the existing port of Muuga, is to handle some five million tons of Siberian coal a year for destinations worldwide. The coal is shipped to Muuga by rail. Future developments may include container berths and steel facilities. The main contractor for the development of the Muuga coal terminal was the Estonian project management group A.S. Merko Ehitus. The dredging subcontract was awarded in late May 2003 to Terramare Eesti O.Ü., the Estonian arm of the Finnish-based Boskalis group company Terramare Oy.

29_Oct_04_D_isle__1__header.jpg

Construction drilling island and ice barriers, Kazakhstan

Agip Kazakhstan North Caspian Operating Company B.V. (Agip KCO), a consortium of eight leading oil companies, is active in the northern section of the Caspian Sea. The gas and oil reserves in this area were mapped out in 1998 and 1999. To allow for their exploitation, Boskalis International has created an artificial island measuring 225 x 225 meters, and underwater berms, for Agip KCO. Four years later, the time was ripe for the construction of the drilling island and ice barriers. Once they were in place, Agip KCO could start to extract and distribute the oil reserves.

Queen_Daya_Bay_300dpi_header.jpg

Port construction, Daya Bay

In Daya Bay, P.R. China, a USD 4.3 billion petrochemicals complex was being built by CNOOC and Shell Petrochemicals Company (CSPC). Daya Bay is located in the southwest of China, Huizhou Municipality, Guangdong Province. The project called for the construction of two marine facilities, one nearby the petrochemicals complex, the other one further offshore. Early 2004, the Boskalis International B.V. and Nanjing Changjiang Waterway Engineering Bureau (NCWEB) partnership commenced dredging for the CSPC Nanhai Petrochemicals project. Key requirement of the project was to preserve the sensitive environment in Daya Bay. Hydronamic, Boskalis’ own engineering consultancy, designed the required monitoring plan and took responsibility for its implementation.

luchtfoto_project.jpg

Creation artificial lagoon, Barcelona

Increasing or compensating nature is one of the challenges in modern infrastructural projects. Within the scope of the extension of the Port of Barcelona compensation was required for nature to be preserved. A natural reserve, south of the Port of Barcelona and north of the International Airport of Barcelona, had to be increased and was realized within the city limits of Prat de LLobregat by the use of the cutter suction dredger Para and its auxiliary equipment.

May_2004_header.jpg

Port development, Coega

The Coega port project - on Algoa Bay at the mouth of Coega River - is designed to act as a catalyst for regional economic development. The new port and its adjacent Industrial Development Zone, 20 km east of Port Elizabeth, are described as South Africa's largest infrastructural development scheme for a decade. 

LFH241124009_header.jpg

Cleanup petroleum harbor, Amsterdam

The Amsterdam Petroleum harbor on the North Sea Canal has been used for the storage and transshipment of oil products since its construction in 1887. Over many years routine operations and unchecked discharges resulted in severe contamination of the harbor.