Port expansion, Ras Laffan

The Ras Laffan project is one of the largest maritime engineering projects in the world. Its sheer size can best be viewed from space. Over a period of three years, more than 3,000 specialists have been working together to create the largest LNG harbor in the world. The total contract value is approximately USD 2 billion, with the Boskalis share amounting to 50%. Qatar has natural gas reserves of roughly 25 trillion m<sup>3</sup>, 15% of the world total. The gas is transported from the Offshore North Field (26,000 billion m<sup>3</sup>), 80 kilometers north of Qatar, into Ras Laffan, where it is liquefied and pumped into latest generation tankers.

This expansion made it necessary to review the infrastructure of both the petro-chemical installations and the facilities for transportation of the products. The new facilities were to be positioned in a sheltered area. The size of the existing harbor had to be increased from 106 km2 to 246 km2. Upon completion, the harbor has 10 loading facilities.To facilitate LNG berths and many other related activities (cargo, gas-2- liquid products etc.) the following additional works had to be constructed:

  • Facilities for LNG tankers;
  • Liquid-product berthing facilities;
  • Cargo on- & offloading facilities;
  • Vessel repair / dry-dock facilities.

As part of this immense expansion the existing port had to be extended from 8 km2 to 51.2 km2. This project was awarded to Boskalis - Jan de Nul JV.

Project specification

The main activities under the contract were:

  • 24 million m3 dredging of waterways (widening of the existing waterways and additional shelters)
  • 29 million m3 reclamation (areas for tank storage, container handling and future dry docks)
  • The construction of 33 kilometers of breakwaters, for which the following materials were required:

31 million tons of local rock material, 9 million tons of rock from overseas, transported over a distance of 275 n. M., 2.5 million m3 of concrete and 250,000 concrete elements for protection of the structures against wave conditions (Antifers & Accropodes of 3, 4 and 5 m3 each).

Related projects

Selected filters
IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.

DSC04359_header.jpg

Port access channel dredging, Walvis Bay

The port of Walvis Bay is a naturally sheltered deepwater harbor on the west coast of Africa. The port is part of a transit route linking Southern Africa, Europe and the Americas and it is Namibia’s largest commercial port, handling around 5 million tons of cargo each year. The container terminal can accommodate a throughput of about 250,000 containers per year.