To main content

Re-insulation Gannet 'C' Bundles, North Sea

The Gannet 'C' satellite field, which is located in the North Sea at 112 miles East of Aberdeen in 95-meter water depth, comprises four drill centres, each having one or more producing wells. The drill centres are connected to the local platform Gannet 'A' by four flowline bundles with a total length of 10 kilometers. A glycol-based gel, filling the annulus of the Gannet 'C' carrier pipe, insulated the individual flow lines. Prompted by degradation of the gel and the resulting drop in oil and gas arrival temperatures at the platform, an EPIC project took off for a re-insulation system. The objective of the re-insulation system was that it should provide sufficient insulation to the bundles in order to safeguard production during the total field life of Gannet 'C', being a minimum lifetime of 15 years. Boskalis Offshore was supported by Hydronamic - the in-house engineering department.

Early July 1997, the installation commenced. Trailing Suction Hopper Dredger WD Fairway and dynamically positioned fallpipe vessel Sandpiper were employed for sand berm and rock cap construction respectively. The sand winning area was found in the outermost northern edge of the Dutch continental shelf, at about 225 kilometer distance from the Gannet field. The local dredging depth was 45 meters. Only one of the two suction pipes was predestined for dredging. For purpose of controlled sand depositing at 95 meter water depth the other pipe was extended, fitted with plates inside and equipped with a purpose-built diffuser at its end. In all WD Fairway deposited approximately 1,500,000 m3 sand at a gross production rate of 100,000 m3 per week. This rate included dredging, sailing, depositing, survey, crew change and weather delay. Sailing speeds up to 16 knots and hopper load volumes up to 18,000 m3 were obtained. Sandpiper, using an innovative fallpipe technique with polyethylene pipe segments, loaded the gravel material at a Norwegian quarry at about 300 kilometer distance of the Gannet field. In all about 130,000 tonnes of gravel was placed on top of the sand berm for stability and insulation. Early January 1998 the gravel dump works were completed.

Related projects

Selected filters
TSHD_Queen_of_the_Netherlands_dredging_hard_spot_close_to_the_existing_SPM_header.jpg

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

131007_1_Sunset_in_the_field_header.jpg

Mooring installation and hook-up, OSX3

OGX - OSX is a Brazilian oil and gas company owning and operating several floating facilities in Brazil. MODEC secured the FPSO purchase contract and subsequently awarded Boskalis the Mooring Installation & Hook-up contract. The FPSO had to be installed in the Tubarão Martelo Field, located in the Campos Basin, Brazil, in 105 meters water depth.

IMG_0814_header.jpg

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

NWS_Barge_near_completion_header.jpg

Refurbishment water station, Olero Creek

In November 2010 Chevron Nigeria Limited (CNL) awarded the contract to refurbish this facility to Saipem Contracting Nigeria Limited (SCNL) with Nigerian Westminster Dredging and Marine Limited (NWDM) as subcontractor. The Olero Creek Restoration Project (OCR) is a 70 million US$ construction and commissioning subcontract. The scope of work is the refurbishment and reinstatement of the North Water Station (NWS) and its hook up to the interconnecting piping at Olero Creek.

Provision and installation of submarine fiber optic cable, Strait of Magellan

In September 2011 Boskalis was awarded a contract worth approximately EUR 30 million to provide and install a submarine fiber optic cable across the Strait of Magellan, Argentina. The contract was awarded by the state-owned corporation AR-SAT (Empresa Argentina de Soluciones Satelitales S.A.).

PAG_9_TRANSPORT_FLEET_SUPPORTS_LINCS_WINDFARM_CONSTRUCTION_-_Groot_header.jpg

Offshore wind farm, LINCS

SMIT Transport is transporting the wind turbine foundations for the new Lincs Offshore Windfarm, situated off Great Yarmouth, UK. When completed, the windfarm will consist of 75 turbines capable of generating sufficient power to meet the annual demand of some 200,000 households.