Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.

River bed protection in front of the quay wall and slope protection on the north and south sides of the quay wall was required to prevent scour by the flow of the river and propeller wash from vessels using the quay wall.

Design of river bed and slope protection

The original design of the river bed and slope protection consisted of Reno mattresses placed on a geotextile, which at the time was considered the preferred option with the aim of reducing rock quantities. However, following a design review by Hydronamic, the Boskalis Engineering Department, and given the technical construction considerations recommended by the Boskalis Rock Department, SPDC later agreed to change the design of the bed protection along the quay wall and slope protection below the LWL along the South Bank, and to install protection consisting of rock armor on a granular filter layer rather than Reno mattresses.

Cooperation Pelfaco Limited and NWDM

SPDC awarded the contract for the river bed and slope protection to Pelfaco Ltd. In early January 2011, NWDM was asked to work with Pelfaco as a sub-contractor in order to ensure that the most critical parts of the site at least would be protected before the next rainy season of 2011. Following the successful completion of these emergency works the cooperation was further extended until the whole of the river bed protection along the quay wall and the slope protection on the South Bank was completed.

Related projects

Selected filters
8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.

IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.