Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.

The cables have the capability to transfer power at 130 MVA per circuit. This project will provide enough additional power to solve Bali's shortage and facilitate the further development of a popular tourist destination, which attracts around 2.3 million tourists each year. Boskalis’ scope ran roughly from the high water mark at Ketapang, Java, to the high water mark at Gilimanuk, Bali and involved the installation of the two submarine cables, including four cable landings. After cable installation, both cables had to be covered with a rock berm over nearly the entire length of the routes. The newly built Cable Laying Vessel (CLV) Ndurance was deployed for the cable installation.

Engineering

One of the most complicating factors was the extremely strong current which occurs in the Bali Strait. Boskalis’ in-house engineering company Hydronamic was involved to analyze the most efficient installation method and period. Based on a current measurement campaign, which lasted over one year, the most favorable installation window was determined. Since Boskalis was also responsible for the cable routes design, an extensive hydrographic survey was undertaken to map the seafloor. This survey and the design parameters specified by the Client were used to design the optimum cable routes, taking the properties of the cables into account. Mitigation of free spans and vortex induced vibrations (VIV) formed part of the engineering work, coordinated by Boskalis' affiliate VBMS. To assess the station keeping capabilities of the Ndurance at this specific location with very strong currents, a series of simulations was performed at the Marin ship simulator. Based on these simulations, it was decided to have an Azimuth Stern Drive (ASD) tug boat stand-by in the direct vicinity of the CLV during cable lay operations to avoid any risk for crew, vessel and cable. Extensive sea trials were undertaken in Singapore and on site to practice and determine the behavior of the Ndurance and the combination of CLV and ASD tug.

Related projects

Selected filters
Fleet_OE_Moho.jpg

Transport and installation Moho Nord FPU

For the Total Moho Nord FPU project, Dockwise has transported the newbuild FPU Likouf from the HHI fabrication yard in Ulsan, South Korea to the offshore discharge location near Port-Gentil, Gabon. It was a world-record cargo load onboard a semi-submersible vessel to date. 

Thien_Ung_I.jpg

Installation topside
and living quarters,
Thien Ung BK-TNG

For the Vietsovpetro Thien Ung project, Boskalis has installed the Thien Ung BK-TNG 4,200 metric tonne (mt) topside and 850 mt living quarter by offshore heavy lifting with the sheerleg Asian Hercules III. It was the world’s heaviest lift installation of a topside by a sheerleg in an offshore environment to date. 

1407-0505-30_header.jpg

Development gas export pipeline, Ichthys

The Ichthys development revolves around the construction of a new 42-inch deep sea natural gas pipeline from the Ichthys field in the Browse Basin 880 kilometers to Darwin onshore. The pipeline will run through the Darwin harbor, requiring dredging services in the near shore area, rock installation and the construction of a landfall. Owner INPEX Operations Australia Pty Ltd is developing LNG process facilities on Blaydin Point near Darwin, Northern Territory of Australia.

140718_-_48.jpg

Wintershall RAVN and A6-A

Wintershall Noordzee B.V. installed a new remote platform RAVN as a crude production tie-back to A6-A. RAVN is a remote and unmanned crude well unit. Utilising a dry-tree design, all control, power and metered injection for the well will be via the 18.2-km control umbilical between the new satellite platform RAVN in the Danish sector and the operational platform A6-A in the German sector.

AT2C5860_header.jpg

Dry transport,
FPSO Armada Intrepid

The Armada Intrepid, which is owned by the Malaysian company Bumi Armada, is an FPSO (Floating Production, Storage and Offloading) vessel which needed to be dry transported from Rotterdam (Netherlands) to Batam (Indonesia) on the Dockwise Vanguard. The FPSO is 245 m long and weighs 60,000 metric tons. The DWV (275 x 70 m) has a deadweight of 117,000 metric tons.

ZP_-_pic4_header.jpg

Mooring replacement phase 2, Zafiro Producer

Mobil Equatorial Guinea Incorporated, an affiliate of ExxonMobil, entered into a contract with Boskalis for the Zafiro Producer Mooring Replacement Project Phase 2. The Zafiro Producer is installed in 180 m (590 ft)water depth approximately 74 km (40 nauticalmiles) west of Malabo, Equatorial Guinea.