Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

The infield cables were loaded in one load-out at Drammen in Norway and then cut down to the correct size on site. The WTGs were connected in a grid of infield cables. 86 individual cables were installed between the turbines, including 6 redundancy cables, amounting to a total length of approximately 90 km for the infield cabling. Cable production commenced in December 2013. The cables were installed in the summer of 2014 using the Stemat Spirit. This vessel was converted to enable the handling of the long cable protection system lengths. Trenching of the cables was performed using a separate trenching spread. Termination, testing and commissioning of the 12 cable strings were carried out using in-house resources.

Related projects

Selected filters
_Group_4_-_DSC7015__DSC7024-3_images_header.jpg

Port development, Tanger Med 2

Tanger-Med is a cargo and passenger port located about 40 km east of Tangiers, Morocco, on the Straits of Gibraltar at the crossing of two major maritime routes only 15 km from the European mainland.

TSHD_Cornelis_Zanen_rainbowing_header.jpg

Port upgrade, Pointe Noire

The rehabilitation of the Port of Pointe-Noire focused on the renovation and upgrading of the main infrastructure of the port and its adaptation to developments in containerized traffic, offering a draught of -15 m. Furthermore, the work included the construction of a protective berm, an extension of the external breakwater, the rehabilitation and extension of quays, and dredging work.

DSC_0602_header.jpg

Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

19DS9430_12-11-26_005_header.jpg

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

Aeroview_D1207-944_header.jpg

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

Gbaran_Ubie_filter_placement_header.jpg

Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.