Construction of greenfield port and breakwater for Dangote quays Lekki

The Dangote Group, owned by Aliko Dangote, is building Africa’s largest oil refinery and fertilizer plant in Lekki, 60 kilometers east of Lagos, Nigeria. To facilitate the import of out-of-gauge components and other materials required for construction activities, a port was constructed

In October 2017, Boskalis was awarded the contract for the dredging of an access channel, a turning circle and a port basin. In addition, Boskalis carried out work to reclaim an innovative sandbar, constructed the sandbar groin and north groin, as well as lee-side and basin revetments. In anticipation of future erosion of the beach to the east of the port, a geo-tubes sleeping defense system and sand engine were built.
In total, Boskalis dredged and reclaimed approximately five million cubic meters of sand and installed close to 300,000 tons of rock and 1,050 concrete  elements (Eko-podes).

DREDGING AND RECLAMATION

For the dredging and reclamation works, Boskalis deployed three of its trailing suction hopper dredgers: Argonaut, Shoalway and Shoreway. Dredging of the harbor basin and turning circle was carried out by the cutter suction dredger Martina, owned and operated by Boskalis’ Nigerian entity Nigerian Westminster Dredging and Marine Limited (NWDM). The reclamation works were supported by the multicats BKM 100 and Nun River, both owned and operated by NWDM. The onshore reclamation spread consisted of four Caterpillar D6 LGP bulldozers, three Caterpillar 966 wheel loaders and two Caterpillar 336 hydraulic excavators. A start was made with the reclamation of the sandbar, which required dredging and reclamation of four million cubic meters of sand. Subsequently, the reclamation of the sand engine was carried out to allow for the installation of the stacked geo-tubes sleeping defense system.

Related projects

Selected filters
Muuga_3_header.jpg

Expansion coal terminal, Muuga

The Muuga Coal terminal, sited on a bay, east of the existing port of Muuga, is to handle some five million tons of Siberian coal a year for destinations worldwide. The coal is shipped to Muuga by rail. Future developments may include container berths and steel facilities. The main contractor for the development of the Muuga coal terminal was the Estonian project management group A.S. Merko Ehitus. The dredging subcontract was awarded in late May 2003 to Terramare Eesti O.Ü., the Estonian arm of the Finnish-based Boskalis group company Terramare Oy.

29_Oct_04_D_isle__1__header.jpg

Construction drilling island and ice barriers, Kazakhstan

Agip Kazakhstan North Caspian Operating Company B.V. (Agip KCO), a consortium of eight leading oil companies, is active in the northern section of the Caspian Sea. The gas and oil reserves in this area were mapped out in 1998 and 1999. To allow for their exploitation, Boskalis International has created an artificial island measuring 225 x 225 meters, and underwater berms, for Agip KCO. Four years later, the time was ripe for the construction of the drilling island and ice barriers. Once they were in place, Agip KCO could start to extract and distribute the oil reserves.

Queen_Daya_Bay_300dpi_header.jpg

Port construction, Daya Bay

In Daya Bay, P.R. China, a USD 4.3 billion petrochemicals complex was being built by CNOOC and Shell Petrochemicals Company (CSPC). Daya Bay is located in the southwest of China, Huizhou Municipality, Guangdong Province. The project called for the construction of two marine facilities, one nearby the petrochemicals complex, the other one further offshore. Early 2004, the Boskalis International B.V. and Nanjing Changjiang Waterway Engineering Bureau (NCWEB) partnership commenced dredging for the CSPC Nanhai Petrochemicals project. Key requirement of the project was to preserve the sensitive environment in Daya Bay. Hydronamic, Boskalis’ own engineering consultancy, designed the required monitoring plan and took responsibility for its implementation.

luchtfoto_project.jpg

Creation artificial lagoon, Barcelona

Increasing or compensating nature is one of the challenges in modern infrastructural projects. Within the scope of the extension of the Port of Barcelona compensation was required for nature to be preserved. A natural reserve, south of the Port of Barcelona and north of the International Airport of Barcelona, had to be increased and was realized within the city limits of Prat de LLobregat by the use of the cutter suction dredger Para and its auxiliary equipment.

May_2004_header.jpg

Port development, Coega

The Coega port project - on Algoa Bay at the mouth of Coega River - is designed to act as a catalyst for regional economic development. The new port and its adjacent Industrial Development Zone, 20 km east of Port Elizabeth, are described as South Africa's largest infrastructural development scheme for a decade. 

LFH241124009_header.jpg

Cleanup petroleum harbor, Amsterdam

The Amsterdam Petroleum harbor on the North Sea Canal has been used for the storage and transshipment of oil products since its construction in 1887. Over many years routine operations and unchecked discharges resulted in severe contamination of the harbor.