To main content

Dredging, reclamation and
shore protection, Soyo LNG

Angola is one of the world’s deep water oil exploration ‘hot spots’. More than 50 significant oil discoveries in Blocks 14, 15, 17 and 18 are believed to contain at least 10 billion barrels of oil. With the increase in oil production comes large quantities of associated gas. Historically, in the absence of a local market, associated gas has been flared or reinjected into the reservoirs. Sonangol, the state oil company, and some of its oil producing partners developed the Angola LNG Project to reduce flaring of gas and curtail gas injection. Angola LNG is a joint venture project involving the major oil producers in the country. Sonangol and Chevron are the co-leaders of the project; the other partners are Total, ENI and BP.

The LNG plant will be built on a site south of the Congo River, in Zaire Province, West of the city of Soyo. The plant will have a capacity of 5.0 million tonnes per year, a full containment LNG storage, a LPG and condensate storage and a loading jetty. Angola LNG Limited awarded the contract for preparation of the plant site to the joint venture of Boskalis International B.V. and Jan de Nul Dredging Ltd., in which Boskalis had the lead. The preparation of the plant site consisted of widening and deepening the existing shipping channel in the ‘Baia de Diogo Cão’; dredging a turning basin for the LNG facility and improving the existing Kwanda Basin. The volume dredged was 28 million m3. The land reclamation works for the LNG facility consisted of raising 125 hectares of existing land on the north side of Kwanda Island and creating 65 hectares new land in the Congo river estuaria. The reclamation works required a total of 7 million m3 suitable material. Besides dredging and land reclamation, the works involved the construction of 1.5 km shore and slope protection, the installation of 4.5 km drainage around the fill areas, the installation and monitoring of geo instrumentation, the installation of a concrete oil/water separator and floodvalve as well as the placing of navigation aids in the channel and basins. The design and construct works were awarded by the end of January 2007, and all operations had to be completed by December 2008. The works entailed a highly challenging timeline and required a high degree of flexibility as the scope of work changed over time. This demanded maximum adaptability and fast decisionmaking, particularly in the design phase. Extensive environmental mitigation measures presented a further challenge, as did the unexploded bombs and other ordnance lying on the seabed in the area, a legacy from Angola’s 27-year civil war, which ended in 2002.

Related projects

Selected filters
_Group_4_-_DSC7015__DSC7024-3_images_header.jpg

Port development, Tanger Med 2

Tanger-Med is a cargo and passenger port located about 40 km east of Tangiers, Morocco, on the Straits of Gibraltar at the crossing of two major maritime routes only 15 km from the European mainland.

TSHD_Cornelis_Zanen_rainbowing_header.jpg

Port upgrade, Pointe Noire

The rehabilitation of the Port of Pointe-Noire focused on the renovation and upgrading of the main infrastructure of the port and its adaptation to developments in containerized traffic, offering a draught of -15 m. Furthermore, the work included the construction of a protective berm, an extension of the external breakwater, the rehabilitation and extension of quays, and dredging work.

DSC_0602_header.jpg

Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

19DS9430_12-11-26_005_header.jpg

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

Aeroview_D1207-944_header.jpg

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

Gbaran_Ubie_filter_placement_header.jpg

Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.