To main content

Free span rectification gas pipeline, East Java

The existing live 28" East Java Gas Pipeline runs offshore from the Kangean Block, close to Pagerungan Besar Island, Kangean Islands, Indonesia, through the Madura Strait and onshore via Porong to Surabaya, Indonesia’s second largest city.

During a survey campaign in 2006 initiated by the owners of the East Java Gas Pipeline, PT. Pertamina Gas and PT. Trans Javagas Pipeline, a large number of critical spans were identified, many of which above the threshold for vortex induced vibrations. Boskalis Offshore, through its Indonesian entity PT. Boskalis International Indonesia, was contracted to rectify 799 critical spans by means of installing a total of 804 rock berms. These berms reduce span lengths and prevent that the critical span length will be exceeded within the remaining lifetime of the pipeline.

Support Berm Installation 

For the support berm installation works Boskalis deployed its dynamically positioned fallpipe vessel (DPFV) Seahorse. This vessel, with a carrying capacity of 18,000 tons of rock, is able to position its fallpipe directly above the live pipeline, meanwhile ensuring sufficient vertical clearance to compensate for current and swell. The DP Class II capabilities of the vessel allow for accurate dumping with a minimum of losses resulting in a short project execution time. One load of 1-5' rock was brought from Norway and additional loads were loaded in Indonesia. Rock was supplied by a quarry operating in the inlands of East Java, delivering rock via the road to a temporary stockpile at the port of Paiton. During loading the 1-5' rock was transported by truck from the temporary stockpile to the feeder and via a conveyor belt into the holds of the DPFV Seahorse. The entire temporary supply chain for rock supply, from quarry to Seahorse, was purposely set up for the execution of this project. Prior to commencement of the rock dumping operations, a pre-survey was carried out by Seahorse's ROV, equipped with multibeam echosounders. This survey was used to identify the start and end points of the free spans. Subsequently, the design per span location was prepared and the berms were installed. A post-survey was carried out to ensure that the berms were installed as specified. When the results of the post-survey were satisfactory, the vessel moved to the next position.

Related projects

Selected filters
TSHD_Queen_of_the_Netherlands_dredging_hard_spot_close_to_the_existing_SPM_header.jpg

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

131007_1_Sunset_in_the_field_header.jpg

Mooring installation and hook-up, OSX3

OGX - OSX is a Brazilian oil and gas company owning and operating several floating facilities in Brazil. MODEC secured the FPSO purchase contract and subsequently awarded Boskalis the Mooring Installation & Hook-up contract. The FPSO had to be installed in the Tubarão Martelo Field, located in the Campos Basin, Brazil, in 105 meters water depth.

IMG_0814_header.jpg

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

NWS_Barge_near_completion_header.jpg

Refurbishment water station, Olero Creek

In November 2010 Chevron Nigeria Limited (CNL) awarded the contract to refurbish this facility to Saipem Contracting Nigeria Limited (SCNL) with Nigerian Westminster Dredging and Marine Limited (NWDM) as subcontractor. The Olero Creek Restoration Project (OCR) is a 70 million US$ construction and commissioning subcontract. The scope of work is the refurbishment and reinstatement of the North Water Station (NWS) and its hook up to the interconnecting piping at Olero Creek.

Provision and installation of submarine fiber optic cable, Strait of Magellan

In September 2011 Boskalis was awarded a contract worth approximately EUR 30 million to provide and install a submarine fiber optic cable across the Strait of Magellan, Argentina. The contract was awarded by the state-owned corporation AR-SAT (Empresa Argentina de Soluciones Satelitales S.A.).

PAG_9_TRANSPORT_FLEET_SUPPORTS_LINCS_WINDFARM_CONSTRUCTION_-_Groot_header.jpg

Offshore wind farm, LINCS

SMIT Transport is transporting the wind turbine foundations for the new Lincs Offshore Windfarm, situated off Great Yarmouth, UK. When completed, the windfarm will consist of 75 turbines capable of generating sufficient power to meet the annual demand of some 200,000 households.