Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Scope of work

Boskalis mobilized from Indonesia the TSHD Cornelis Zanen with a hopper capacity of 8,600 m3. The channel was deepened to a minimum depth of 6 m CD over the full width of 100 m. In addition, the approach channel was widened to allow vessels more manoeuvring capabilities when entering the inner port.

Challenges

Tight timeline Dredging operations started immediately on the arrival of Cornelis Zanen, leaving limited time for project preparation. Working in close cooperation with the Myanmar Port Authorities and working with local subcontractors and suppliers, the Boskalis project team finalized the bathymetric riverbed survey measurement campaign within several days of signing the contract. River conditions Navigation from the pilot station 32 km seaward of Elephant Point is generally on the flood tide, and to ensure sufficient depth, crossing both the inner bar and outer bar is timed for high tide. The average tidal range is about 6 m at spring tide and 2.5 m at neap tide. While waves in the Yangon River do not hinder maritime operations, the current velocity of 4 to 6 knots at spring tide has to be controlled. As the channel width of 100 m at Monkey Point is relatively limited, navigation and particularly the dredging operations demanded close attention. Safety and cooperation with other parties The Boskalis No Incident and No Accident (NINA) safety program was implemented and within the short time period available, all parties were informed and were fully compliant with the high safety standard throughout the project. 

Conclusion

Boskalis completed the dredging works in compliance with the contract requirements and in partnership with the Myanmar Port Authority. The works were completed within the budget and the required time frame without accident, incident or spill.

Related projects

Selected filters
Loading_TSHD_by_CSD_header.jpg

Creation bird island, Le Havre port 2000

Le Havre is the fifth largest container port in Europe and is expanding its facilities: the current 14 quays for container vessels are to be expanded with another 12 (all outside the locks). Port 2000’s rationale centres on Le Havre’s determination to position itself as a leading hub.

hfd_onder_header.jpg

Creating two berths pockets, NCIG terminal

For 200 years the Port of Newcastle has been Australia’s premier coal export harbor. Of the 95 Mtpa of various commodities such as steel, aluminum, minerals and so forth exported from Newcastle in 2008-2009, 90.5 Mtpa were attributable to coal. Average annual growth rate of coal exports from 1990 to 2006 was 6.1%. This constant increase has caused a spike in ships queuing to enter the harbour to be loaded. To increase capacity and avoid these traffic jams, a decision was made to develop a new coal stockpile area and construct a third coal terminal.

Balboa_2_header.jpg

Port expansion, Balboa

The plans to expand the Panama Canal represent one of the most important infrastructure improvements of the 21st century. Since its opening in 1913 the Canal has provided the shortest and most economically viable shipping route from Pacific to Atlantic seaports. With the ever-increasing size of modern-day vessels, it was inevitable that the Canal would need to be widened and deepened. The expansion of the Canal has made the extension of the Port of Balboa at the mouth of the canal on the Pacific Ocean a necessity. The Phase 4 projects included Marine Works and Civil Works to improve two existing berths and to build a completely new berth capable of handling not only Post Panamax but also Super Post Panamax ships.

DSCF0226_header.jpg

Land reclamation, North Manama Causeway

The purpose of the project was to provide additional land to accommodate a section of a proposed new highway system to service the area and to relieve congestion on the corniche road. Boskalis appointed Hydronamic (the in-house engineering department of Boskalis) to provide detailed design and on site assistance with supervision of the sub-contractor for the rock works.

Figure_1_header.jpg

Port environmental mitigation measures, Hamina

Hamina, which is close to the Russian border in south-east Finland, is a home port for the oil industry and a transit harbor for timber, cars and other goods on their way to Russia. To provide access for larger vessels it had to deepen the existing channel by two meters to 12 meters and create a new channel section. Terramare Oy, a subsidiary of Royal Boskalis Westminster, won this assignment in late 2008. The project started in July 2009.

Raahe_1_header.jpg

Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.