To main content

Outer harbor channel widening, Adelaide.

The Port of Adelaide is the primary port in South Australia, located at Outer Harbor. The port is operated by Flinders Ports Pty Ltd (Flinders Ports) and handles both container and cruise vessels, contributing significantly to the State’s economic activity. Flinders Ports identified the need for an upgrade of the existing infrastructure driven by the emergence of Post Panamax class vessels. To meet this growth the existing channel had to be widened to accommodate vessels with a maximum width of 49 m without operational restrictions. Flinders Ports contracted Boskalis to execute the dredging works.

SCOPE

Dredging works included the widening of the existing access channel by 40 m to a total width of 170 m and the swing basin from 505 to 560 m and to a depth of -14.2 m LAT. The dredged material was transported to a designated dredge material placement area, located approximately 30 km offshore in the Gulf of St. Vincent. Dredging works were undertaken by the TSHD Gateway and the BHD Magnor assisted by a plough vessel and barges. A total volume of 1.5 million m3 nett was dredged in approximately 3 months.

EARLY CONTRACTOR INVOLVEMENT

Boskalis was appointed as preferred contractor in October 2018 and assisted from this moment in time in obtaining the Dredge Licence together with Flinders Ports, engineering consultant Arup and environmental consultant BMT. The dredge licence was granted by the Environmental Protection Agency of South Australia (EPA) on the 12th of March 2019. Environmental management plans were written in close collaboration between all parties, ensuring commencement of dredging works in time.

ENVIRONMENT

Environmental protection was of utmost importance for the executing of the project. Seagrass meadows are present adjacent the access channel for which stringent turbidity limits applied and seagrass surveys were undertaken prior and post dredging works. The project was partly located in the Adelaide Dolphin Sanctuary, hosting several resident and transient dolphin species, for which marine mammal monitoring was undertaken by the dredge crew. Prior to the works, razorfish present at the seabed in the channel had to be removed to prevent the potential spread of the Pacific Oyster Mortality Syndrome to South Australia’s important oyster farming industry. Finally, the overseas and interstate dredge vessels obtained a thorough cleaning prior to arrival in South Australia to adhere to Australia’s biofouling guidelines in order to prevent the importation of invasive marine species.

STAKEHOLDERS

Stakeholder management was key to the project’s success. Flinders Ports conducted a large community engagement campaign, which resulted in no complains during the works. During the works, continuous engagement between the EPA, Boskalis and Flinders Ports occurred to remain informed.

ADAPTIVE MANAGEMENT

During the works, dredge activities had to be managed to remain within the set turbidity thresholds. This was done through The Adaptive Management System in close cooperation with the client and the Environmental Protection Agency. Real-time turbidity monitoring data and knowledge on the operations and the environment ensured effective measures could be taken. During the works however, four events occurred where the upper threshold was exceeded, exuberated by severe weather. The EPA acknowledged that poor weather conditions contributed to the high turbidity levels on occasion and allowed the dredge operation to continue without harming the environment.

TEAM-WORK

The spirit of cooperation and the open communication within in the project team, as well with the Client and relevant stakeholders was excellent. It's also worth mentioning that almost half the project team consisted of female colleagues working on board of dredgers, on hydrographic surveys, environmental issues, planning, logistics and the secretarial side.

SAFETY

To prevent incidents during mooring and unmooring, the BHD Magnor is equipped with a mooring actuator. The mooring actuator was developed to eliminate personnel risks and to optimize the dredging process. The system is a remotely constant tensioning mooring system, which eliminates the need to manually handle the mooring lines for the barges coming along side to be loaded.However no firm requirement, but as a result of increasing awareness for pollution, biodegradable hydraulic oil was used in all the hydraulic systems on the project.

HR

All vessels on the project were operated by a mix of expatriate professionals and Australian seafarers. Personnel was given project specific training to assure the best outcome for the project:

  • Mammal observation training

  • Heritage training

  • Environmental compliance training

  • Project and visitor inductions

Related projects

Selected filters
Muuga_3_header.jpg

Expansion coal terminal, Muuga

The Muuga Coal terminal, sited on a bay, east of the existing port of Muuga, is to handle some five million tons of Siberian coal a year for destinations worldwide. The coal is shipped to Muuga by rail. Future developments may include container berths and steel facilities. The main contractor for the development of the Muuga coal terminal was the Estonian project management group A.S. Merko Ehitus. The dredging subcontract was awarded in late May 2003 to Terramare Eesti O.Ü., the Estonian arm of the Finnish-based Boskalis group company Terramare Oy.

29_Oct_04_D_isle__1__header.jpg

Construction drilling island and ice barriers, Kazakhstan

Agip Kazakhstan North Caspian Operating Company B.V. (Agip KCO), a consortium of eight leading oil companies, is active in the northern section of the Caspian Sea. The gas and oil reserves in this area were mapped out in 1998 and 1999. To allow for their exploitation, Boskalis International has created an artificial island measuring 225 x 225 meters, and underwater berms, for Agip KCO. Four years later, the time was ripe for the construction of the drilling island and ice barriers. Once they were in place, Agip KCO could start to extract and distribute the oil reserves.

Queen_Daya_Bay_300dpi_header.jpg

Port construction, Daya Bay

In Daya Bay, P.R. China, a USD 4.3 billion petrochemicals complex was being built by CNOOC and Shell Petrochemicals Company (CSPC). Daya Bay is located in the southwest of China, Huizhou Municipality, Guangdong Province. The project called for the construction of two marine facilities, one nearby the petrochemicals complex, the other one further offshore. Early 2004, the Boskalis International B.V. and Nanjing Changjiang Waterway Engineering Bureau (NCWEB) partnership commenced dredging for the CSPC Nanhai Petrochemicals project. Key requirement of the project was to preserve the sensitive environment in Daya Bay. Hydronamic, Boskalis’ own engineering consultancy, designed the required monitoring plan and took responsibility for its implementation.

luchtfoto_project.jpg

Creation artificial lagoon, Barcelona

Increasing or compensating nature is one of the challenges in modern infrastructural projects. Within the scope of the extension of the Port of Barcelona compensation was required for nature to be preserved. A natural reserve, south of the Port of Barcelona and north of the International Airport of Barcelona, had to be increased and was realized within the city limits of Prat de LLobregat by the use of the cutter suction dredger Para and its auxiliary equipment.

May_2004_header.jpg

Port development, Coega

The Coega port project - on Algoa Bay at the mouth of Coega River - is designed to act as a catalyst for regional economic development. The new port and its adjacent Industrial Development Zone, 20 km east of Port Elizabeth, are described as South Africa's largest infrastructural development scheme for a decade. 

LFH241124009_header.jpg

Cleanup petroleum harbor, Amsterdam

The Amsterdam Petroleum harbor on the North Sea Canal has been used for the storage and transshipment of oil products since its construction in 1887. Over many years routine operations and unchecked discharges resulted in severe contamination of the harbor.