Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

The oldest Maersk Oil field, Dan Bravo, is located in the Danish sector of the North Sea. The first platform in the complex was installed in 1972. The complex consists of platforms A, B, C and D. The Dan B platform forms the production hub of the Dan Bravo Complex and Dan A platform is one of the wellhead platforms at the Dan Bravo complex. Maersk Oil decided to carry out a platform lifetime extension program for the forty year old jacket structure to extend the service period of the structure until 2042.

General summary of the work scope

  • Reduce sea wave load unto the jacket structure by removing old boat fenders and pump caissons.
  • Inspection history enhancement by investigating all available inspection data, searching for known cracks in the subsea structure and inspecting potential problem areas.
  • Remove crack or damaged areas and replace with new structure (e.g. conductor guide level).
  • Reinforce subsea structure by adding retrofit (clamped) structures to strengthen key areas.
  • Renew consumables by retrofitting additional anodes by means of clamps due to depletion and removing some of the original anodes.
The 2013 offshore campaign started in July and was completed in September. During this campaign Boskalis performed the 3D subsea photogrammetry activities, classified as world’s largest ever undertaken, by air/saturation diving and ROV operations acquiring exact geometrical information of subsea K-joints to be able to design reinforcement clamps. Operations were performed on depths varying from 10 to 41 meters. Besides the technical challenges the environmental conditions as sea-state, fog and subsea reduced visibility (minimum 2 meter required for image taking) dictated the progress of the work.

Related projects

Selected filters
005dd16062014Boskalis-_c_Kloet_header.jpg

Transport and installation depletion compression platform,
Malampaya phase 3

The Malampaya Deep Water Gas-to-Power Project is a joint venture involving the Philippine National Oil Company, Chevron and Shell Philippines Exploration. The project is part of the optimization of the Malampaya gas field which will lead to an eight-year lifetime extension.

SMIT_Subsea_Constructor-MaerskOil_Dan_56768_header.jpg

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

Fairmount_Sherpa_assisted_by_local_harbor_tugs_towing_in_the_FPSO_at_Haugesund_header.jpg

Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

140718_-_48.jpg

Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

DONG_Rockpiper_West_of_Duddon_Sands_header.jpg

Wind farm foundation installation, West of Duddon Sands

With 108 wind turbines producing almost 400 megawatts, West of Duddon Sands is one of the larger European wind farms. It is being built by a joint venture of Dong Energy and Scottish Power Renewables. Boskalis Offshore and Volker Stevin Offshore - in an Offshore WindForce joint venture - were responsible for the transport and installation of the 108 foundations for the wind farm.

Java-Bali_header.jpg

Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.