Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

The oldest Maersk Oil field, Dan Bravo, is located in the Danish sector of the North Sea. The first platform in the complex was installed in 1972. The complex consists of platforms A, B, C and D. The Dan B platform forms the production hub of the Dan Bravo Complex and Dan A platform is one of the wellhead platforms at the Dan Bravo complex. Maersk Oil decided to carry out a platform lifetime extension program for the forty year old jacket structure to extend the service period of the structure until 2042.

General summary of the work scope

  • Reduce sea wave load unto the jacket structure by removing old boat fenders and pump caissons.
  • Inspection history enhancement by investigating all available inspection data, searching for known cracks in the subsea structure and inspecting potential problem areas.
  • Remove crack or damaged areas and replace with new structure (e.g. conductor guide level).
  • Reinforce subsea structure by adding retrofit (clamped) structures to strengthen key areas.
  • Renew consumables by retrofitting additional anodes by means of clamps due to depletion and removing some of the original anodes.
The 2013 offshore campaign started in July and was completed in September. During this campaign Boskalis performed the 3D subsea photogrammetry activities, classified as world’s largest ever undertaken, by air/saturation diving and ROV operations acquiring exact geometrical information of subsea K-joints to be able to design reinforcement clamps. Operations were performed on depths varying from 10 to 41 meters. Besides the technical challenges the environmental conditions as sea-state, fog and subsea reduced visibility (minimum 2 meter required for image taking) dictated the progress of the work.

Related projects

Selected filters
TSHD_Queen_of_the_Netherlands_dredging_hard_spot_close_to_the_existing_SPM_header.jpg

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

131007_1_Sunset_in_the_field_header.jpg

Mooring installation and hook-up, OSX3

OGX - OSX is a Brazilian oil and gas company owning and operating several floating facilities in Brazil. MODEC secured the FPSO purchase contract and subsequently awarded Boskalis the Mooring Installation & Hook-up contract. The FPSO had to be installed in the Tubarão Martelo Field, located in the Campos Basin, Brazil, in 105 meters water depth.

IMG_0814_header.jpg

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

NWS_Barge_near_completion_header.jpg

Refurbishment water station, Olero Creek

In November 2010 Chevron Nigeria Limited (CNL) awarded the contract to refurbish this facility to Saipem Contracting Nigeria Limited (SCNL) with Nigerian Westminster Dredging and Marine Limited (NWDM) as subcontractor. The Olero Creek Restoration Project (OCR) is a 70 million US$ construction and commissioning subcontract. The scope of work is the refurbishment and reinstatement of the North Water Station (NWS) and its hook up to the interconnecting piping at Olero Creek.

Provision and installation of submarine fiber optic cable, Strait of Magellan

In September 2011 Boskalis was awarded a contract worth approximately EUR 30 million to provide and install a submarine fiber optic cable across the Strait of Magellan, Argentina. The contract was awarded by the state-owned corporation AR-SAT (Empresa Argentina de Soluciones Satelitales S.A.).

PAG_9_TRANSPORT_FLEET_SUPPORTS_LINCS_WINDFARM_CONSTRUCTION_-_Groot_header.jpg

Offshore wind farm, LINCS

SMIT Transport is transporting the wind turbine foundations for the new Lincs Offshore Windfarm, situated off Great Yarmouth, UK. When completed, the windfarm will consist of 75 turbines capable of generating sufficient power to meet the annual demand of some 200,000 households.