Port development, Raahe

The Raahe project is the largest dredging contract in Finnish history. Access for larger ships is economically important for the clients using the port of Raahe, such as the steel company Ruukki.

So it was decided to deepen the entrance channel and to extend the port, creating more land by reclaiming the dredged material from the basin and allowing large container vessels and bulk carriers to enter the extended part of the basin. The port extension eliminates the need to transship goods at sea using barges. The project was carried out by Terramare OY (Finland), the Finnish operating company of the RBW group. The project consisted of 4 separate sections:

  • Construction of a fill area in the basin area;
  • Capital dredging of the basin area and reclaiming this material into the fill area;
  • Removal of the existing breakwater;
  • Capital dredging of the 10 km long entrance channel / fairway. 

Related projects

Selected filters
TSHD_Cornelis_Zanen_rainbowing_header.jpg

Port upgrade, Pointe Noire

The rehabilitation of the Port of Pointe-Noire focused on the renovation and upgrading of the main infrastructure of the port and its adaptation to developments in containerized traffic, offering a draught of -15 m. Furthermore, the work included the construction of a protective berm, an extension of the external breakwater, the rehabilitation and extension of quays, and dredging work.

DSC_0602_header.jpg

Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

19DS9430_12-11-26_005_header.jpg

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

Aeroview_D1207-944_header.jpg

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

Gbaran_Ubie_filter_placement_header.jpg

Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.

8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.