Açu Port in São João da Barra, Rio de Janeiro (Brazil) is one of the largest port-industry complex in Latin America. The port consists of two terminals: T1, an offshore terminal for handling iron ore and oil, and T2, an onshore terminal built around the inner navigation channel which accommodates offshore supply companies and will handle bauxite, general cargo and vehicles.

Scope of works 

Boskalis was responsible for the following scope of works on the onshore T2 terminal:

  • Offshore Access Channel, approximately 4,600m long, 300m wide and 14.5m depth;
  • Onshore Access Channel, approximately 2,000m long, 300m wide and 14.5m depth;
  • Turning Basin, with 600m diameter and 14.5m depth;
  • Inner Channel and mooring berths, approximately 3,600m long, widths ranging from 135m, 210m to 500m and depths ranging from 10/11 to 14.5m.

Boskalis was also responsible for project management, the construction of access roadways, clearance of work sites and the construction of revetments at the entrance to the port. The project developed continuously. During the course of the project the nature, dimensions and technical requirements were adapted in line with the changing requirements of the client and other stakeholders such as the future concessionaries of the Port of Açu. Based on continuous interaction with the client the most efficient, technically optimal and cost-effective solutions were adopted to the full satisfaction of all stakeholders. Boskalis also deepened the access channel and the turning basin of the T1 offshore terminal.

Related projects

Selected filters
FF66817_header.jpg

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Cornelis_Zanen.jpg

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Gabon_Libreville1920.jpg

Port development,
Libreville - Gabon

A new area was constructed in the Port of Libreville for a mineral terminal, dry dock, fishing port, processing facilities and other port activities, such as aggregate processing. This new port development was required to improve and strengthen the logistic capacity for the inland mining industry, to reduce export costs, and thus to increase the competitiveness of mineral exports from Gabon.

Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

IMG_3549_header.jpg

Cleanup sediment treatment, Fox river

As a result of industrialization the riverbed of the Fox River (Wisconsin, USA) had become contaminated with PCBs (polychlorinated biphenyls). Joining together a number of large paper mills based on the banks of the river have established the Fox River Cleanup Group to handle the remediation project. The site is on the federal Superfund program’s National Priorities List.

Large-12_overige_financiele_ontwikkelingen.jpg

Cieg GJ1 Cable repair

Channel Islands Electricity Grid, a joint venture between Jersey Electricity and Guernsey Electricity operate several interconnecting power cable systems (power and telecom) between Jersey, Guernsey and France. Both Jersey and Guernsey rely upon the services of these interconnecting power cables and as a consequence there is a demand to reduce the possible effects and impact of failure to these interconnecting power cables. Boskalis were contracted to conduct a preemptive repair replacing a section of cable including the installation two subsea joints on the Guernsey Jersey circuit, close to Havelet bay.