Seabed preparations, PGN

The pipeline between Pulau Pemping, Indonesia, and Pulau Sakra, Singapore, is the final link of the transportation system for natural gas from onshore fields on South Sumatra to Singapore. The successful completion of the Engineering, Procurement and Construction contracts for the 27-kilometers 28-inch gas pipeline with a 96-core fibre optic cable in one of the busiest ports and shipping traffic zones of the world marked a milestone for Boskalis. The scope of work comprised not only seabed preparations and protective rock berm installation - Boskalis Offshore core activities - but also pipeline manufacturing and installation.

The following comprehensive scope of work has been completed on a lump sum basis in two countries, with two clients and under three different contracts:

  • Construction of two landfalls: a cofferdam and 200-meters pipe pull at Pulau Sakra and a trench in shallow reef with 700-meters pipe pull at Pulau Pemping.
  • Seabed preparation for pipe lay: trench dredging and seabed levelling.
  • Procurement and installation of 28-inch concrete coated line pipe, grade X-70, and 96-core double armoured fibre optic cable.
  • Design verification of both a rock berm (drop and drag of 22-tonnes anchors in Singapore waters) and its filter layer (impact on cable of falling rock).
  • Procurement of 2,150,000 tonnes of rock armour and filter material and installation over a length of 25 kilometers.
  • Hydro-testing, drying and precommissioning of pipeline system.

Related projects

Selected filters
TSHD_Queen_of_the_Netherlands_dredging_hard_spot_close_to_the_existing_SPM_header.jpg

Subsea pipeline repair, Bukom SBM

The Shell Bukom Refinery on Bukom Island imports the bulk of its crude oil feedstock through a Single Buoy Mooring (SBM) situated approximately 5.2 km from the island in the deeper water necessary to accommodate Very Large Crude Carriers.

131007_1_Sunset_in_the_field_header.jpg

Mooring installation and hook-up, OSX3

OGX - OSX is a Brazilian oil and gas company owning and operating several floating facilities in Brazil. MODEC secured the FPSO purchase contract and subsequently awarded Boskalis the Mooring Installation & Hook-up contract. The FPSO had to be installed in the Tubarão Martelo Field, located in the Campos Basin, Brazil, in 105 meters water depth.

IMG_0814_header.jpg

Dredging, Sealine COEFR

The Crude Oil Export Facility Reconstruction (COEFR) Project aims to stabilize and expand Iraq’s crude oil export capacity, a lifeline of the Iraqi economy, by constructing a pipeline connecting crude oil storage facilities to the offshore crude oil export terminal in Fao, Basrah in Southern Iraq. The Project involves the development of two offshore valve station platforms, a 75 kilometer 48” oil pipeline and a Single Point Mooring system.

NWS_Barge_near_completion_header.jpg

Refurbishment water station, Olero Creek

In November 2010 Chevron Nigeria Limited (CNL) awarded the contract to refurbish this facility to Saipem Contracting Nigeria Limited (SCNL) with Nigerian Westminster Dredging and Marine Limited (NWDM) as subcontractor. The Olero Creek Restoration Project (OCR) is a 70 million US$ construction and commissioning subcontract. The scope of work is the refurbishment and reinstatement of the North Water Station (NWS) and its hook up to the interconnecting piping at Olero Creek.

Provision and installation of submarine fiber optic cable, Strait of Magellan

In September 2011 Boskalis was awarded a contract worth approximately EUR 30 million to provide and install a submarine fiber optic cable across the Strait of Magellan, Argentina. The contract was awarded by the state-owned corporation AR-SAT (Empresa Argentina de Soluciones Satelitales S.A.).

PAG_9_TRANSPORT_FLEET_SUPPORTS_LINCS_WINDFARM_CONSTRUCTION_-_Groot_header.jpg

Offshore wind farm, LINCS

SMIT Transport is transporting the wind turbine foundations for the new Lincs Offshore Windfarm, situated off Great Yarmouth, UK. When completed, the windfarm will consist of 75 turbines capable of generating sufficient power to meet the annual demand of some 200,000 households.