The Republic of the Maldives consists of 1,190 small coral islands grouped into 26 atolls. Only 200 islands are inhabited. On 26 December 2004, a tsunami originating from Indonesian waters struck the Maldives. This natural disaster had major economic, social and environmental consequences. Of the 200 inhabited islands, 13 were totally destroyed and 56 suffered major damage, including the island of Vilufushi in Thaa Atoll. Houses and infrastructure were heavily damaged. All the surviving residents had to be evacuated to the neighboring island of Buruni to the west of Vilufushi. The government of the Maldives decided to reconstruct the entire island and to extend it considerably by landfilling the shallow reef. Boskalis International was appointed for this work.

Several alternatives were studied. The plan that was finally adopted involved dredging coral sand from an area off the northern reef edge of Vilufushi with a medium-sized cutter suction dredger. The sand was then pumped directly into the area to be filled. The reconstruction included:

  • Removal of all debris.
  • Dredging and reclamation of 1 million m3 of coral sand from the reef to increase the surface of, and raise, the island.
  • Construction of a 2000 meter rock revetment around the island as a breakwater to protect against wave penetration.
  • Dredging of a new harbor to 3 meters below sea level.
  • Construction of a 350 meter quay wall using pre-cast concrete elements.
  • Construction of a 350 meter breakwater to protect against wave penetration. 

Monitoring during dredging and reclamation

The Maldives have a very rich marine biodiversity, which requires safeguarding through special measures, in particular during dredging and reclamation activities. A special monitoring program was required to monitor changes in environmental parameters with an adverse impact.

Related projects

Selected filters

Shell Malikai

Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell Petroleum Company is the designated Operator. A floating Dry Tree Unit (DTU) will be installed over Malikai field utilizing a Tension Leg Platform (TLP) design that suits the Malikai environment.

FF66817_header.jpg

Coastal development, Hondsbossche and
Pettemer Sea Defense

A joint venture of Boskalis Nederland and Van Oord has been commissioned by the Hollands Noorderkwartier water control board to reinforce the Hondsbossche and Pettemer Sea Defense between the villages of Petten and Camperduin on the coast of the Dutch province of Noord-Holland.

Cornelis_Zanen.jpg

Maintenance dredging, Yangon River

Located close to the city centre on the Yangon River, Yangon Port has been the main port to Myanmar since colonial times. Currently, the port has capacity for vessels of up to 15,000 –20,000 DWT and works are scheduled to increase the port’s capacity for vessels up to 35,000 DWT.

Gabon_Libreville1920.jpg

Port development,
Libreville - Gabon

A new area was constructed in the Port of Libreville for a mineral terminal, dry dock, fishing port, processing facilities and other port activities, such as aggregate processing. This new port development was required to improve and strengthen the logistic capacity for the inland mining industry, to reduce export costs, and thus to increase the competitiveness of mineral exports from Gabon.

Butendiek OWF

Boskalis was contracted by OWP Butendiek GmbH & Co. KG to supply, install and protect (by post-lay burial) the high-voltage inter-array cable at the offshore wind farm of Butendiek. This German wind farm is situated in the German Bight (Nordsea), approx. 35 km west of the island of Sylt. The 33 km2 wind farm consists of 80 wind turbines with a capacity of 3.6 MW each and a total capacity of 288 MW. The inauguration of the wind farm took place on September 8, 2015. It provides renew-able energy to approx. 370,000 households.

IMG_3549_header.jpg

Cleanup sediment treatment, Fox river

As a result of industrialization the riverbed of the Fox River (Wisconsin, USA) had become contaminated with PCBs (polychlorinated biphenyls). Joining together a number of large paper mills based on the banks of the river have established the Fox River Cleanup Group to handle the remediation project. The site is on the federal Superfund program’s National Priorities List.