Shell Malikai

Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell Petroleum Company is the designated Operator. A floating Dry Tree Unit (DTU) will be installed over Malikai field utilizing a Tension Leg Platform (TLP) design that suits the Malikai environment.

The 27,500 MT Malikai TLP is to be located about 110 km off the shore of Sabah (East Malaysia) in the South China Sea in water depth about 500 m. Boskalis was awarded a contract in 2014 for the provision of the Heay Transport Vessel (HTV) for loadout and float-off package of the Project which includes loadout of the Integrated Malikai TLP from MMHE fabrication Yard into HTV, Dry-transport to Johor Buoy, Float-off, Tow back and Re-delivery to TMJV at MMHE fabrication yard.

SCOPE

  • Loadout, Transport and Float-off Engineering
  • Design, construct and installation of grillages, skid beams and seafastening Preparation and Mobilization of White Marlin
  • Ballasting of the HTV during the skidded loadout operation
  • Provision of marine spread for the float off operation
  • Demobilization of White Marlin and reinstatement

PROJECT CHALLENGES
Technical challenges included the ability to adapt and successfully perform:

  • The discharge of the TLP offshore in Desaru instead of the original location of Johor Port;
  • The loadout of the integrated TLP ballasted instead of un-ballasted prior to loadout
  • The outfit of a HTV in Vietnam for the first time

NINA
The project was executed without incident. The NINA initiative was not only inculcated within the Boskalis PMT but also with key subcontractors.

CONCLUSION
The success of the project was due to the strong colaboration between all parties. The loadout oper-ation had several difficult challenges; technically and operationally. However, this was all resolved through communica-tion and the close cooperation between TMJV and Boskalis, which ensured that the TLP was still loaded in a safe, operationally sound and timely manner.

Related projects

Selected filters
8620740517_e75a0d7703_o_1__header.jpg

Reinforcing Dutch
coastline, Sandmotor

In December 2010 Royal Boskalis Westminster N.V. was awarded a contract by the Dutch Directorate General for Public Works and Water Management to reinforce part of the coastline in the province of Zuid-Holland by creating a ‘sand engine’. The total value of the contract is EUR 50 million for the Van Oord- Boskalis consortium, in which Boskalis has a 50% stake.

IMG_1101_header.jpg

Port expansion LNG terminal, Cuyutlán

The Mexican Ministry of Communications and Transport awarded Royal Boskalis Westminster N.V. two contracts for dredging an access channel and turning basin at the Cuyutlán liquefied natural gas import terminal on the west coast of Mexico.

Oranje___CDF_31Oct11__2__-_aangepast_header.jpg

Design and construction harbor channel, Sydney harbor

The 'Sydney Harbor Channel Dredging Project' in Nova Scotia, Canada, involved dredging and reclamation work as part of the construction of the new Sydney Port container terminal located on the northeast coast of Canada. Once operational, Sydney Port will be the most northerly deepwater container terminal on the North American east coast.

9CHP0243_header.jpg

Port construction,
Khalifa port

The Khalifa Port and Industrial Zone (KPIZ), one of the world’s largest greenfield development projects, is part of Abu Dhabi’s major diversification plan to develop various sectors such as property, tourism, infrastructure and others. Abu Dhabi’s main existing port, Mina Zayed, is hemmed in by Abu Dhabi city, limiting its accessibility and the possibility for expansion.

edax_aroima_copy_header.jpg

Maintenance dredging, Berbice River

One of Guyana’s major export products is bauxite, which originates from the Aroaima, Kwakwani and Ituni regions around the Demerara and Berbice rivers in north-eastern Guyana. Guyana annually exports approximately 2.2 million tons of bauxite from it’s mines along the Berbice River. Boskalis International has long been associated with the mining industry in Guyana. In 1990 a long-term overburden removal project for the Aroaima mine was begun in Guyana involving the dredging and disposal of a sand and clay layer of 30-45 meters thickness.

CHP10918_header.jpg

Port reconfiguration, Felixstowe

Capital dredging and filling works for new quay development (previously known as Landguard Redevelopment). Phase 1 of the reconfiguration programme consists of: 730 m new deep water quay and 200,000 m2 container handling area achieved by installing new quay in front of old Landguard port structures and redevelopment of the old Landguard terminal.