Malikai is a deepwater oil discovery in offshore Sabah, Malaysia where Sabah Shell Petroleum Company is the designated Operator. A floating Dry Tree Unit (DTU) will be installed over Malikai field utilizing a Tension Leg Platform (TLP) design that suits the Malikai environment.

The 27,500 MT Malikai TLP is to be located about 110 km off the shore of Sabah (East Malaysia) in the South China Sea in water depth about 500 m. Boskalis was awarded a contract in 2014 for the provision of the Heay Transport Vessel (HTV) for loadout and float-off package of the Project which includes loadout of the Integrated Malikai TLP from MMHE fabrication Yard into HTV, Dry-transport to Johor Buoy, Float-off, Tow back and Re-delivery to TMJV at MMHE fabrication yard.

SCOPE

  • Loadout, Transport and Float-off Engineering
  • Design, construct and installation of grillages, skid beams and seafastening Preparation and Mobilization of White Marlin
  • Ballasting of the HTV during the skidded loadout operation
  • Provision of marine spread for the float off operation
  • Demobilization of White Marlin and reinstatement

PROJECT CHALLENGES
Technical challenges included the ability to adapt and successfully perform:

  • The discharge of the TLP offshore in Desaru instead of the original location of Johor Port;
  • The loadout of the integrated TLP ballasted instead of un-ballasted prior to loadout
  • The outfit of a HTV in Vietnam for the first time

NINA
The project was executed without incident. The NINA initiative was not only inculcated within the Boskalis PMT but also with key subcontractors.

CONCLUSION
The success of the project was due to the strong colaboration between all parties. The loadout oper-ation had several difficult challenges; technically and operationally. However, this was all resolved through communica-tion and the close cooperation between TMJV and Boskalis, which ensured that the TLP was still loaded in a safe, operationally sound and timely manner.

Related projects

Selected filters
_Group_4_-_DSC7015__DSC7024-3_images_header.jpg

Port development, Tanger Med 2

Tanger-Med is a cargo and passenger port located about 40 km east of Tangiers, Morocco, on the Straits of Gibraltar at the crossing of two major maritime routes only 15 km from the European mainland.

TSHD_Cornelis_Zanen_rainbowing_header.jpg

Port upgrade, Pointe Noire

The rehabilitation of the Port of Pointe-Noire focused on the renovation and upgrading of the main infrastructure of the port and its adaptation to developments in containerized traffic, offering a draught of -15 m. Furthermore, the work included the construction of a protective berm, an extension of the external breakwater, the rehabilitation and extension of quays, and dredging work.

DSC_0602_header.jpg

Land reclamation artificial island, Punta Pacifica

The shoreline of Panama has increasingly become densely populated and, as the economy has boomed over the past 10 years, there is strong demand for high-end products. The real-estate market has taken a revolutionary step with the completion of the the first artificial real-estate island in the Americas.

19DS9430_12-11-26_005_header.jpg

Construction LNG port, Swinoujscie

The protective breakwater for Swinoujscie External Port comprises a 3 km long breakwater and groyne for a new outer harbor construction to facilitate a LNG tanker berth and other related activities in the Baltic Sea. The construction of the breakwater took 2 ½ years and was completed in December 2012. Boskalis International B.V. was the leader of a consortium consisting of Boskalis International B.V., Hochtief, Aarsleff and Doraco.

Aeroview_D1207-944_header.jpg

Port expansion,
Maasvlakte 2

PUMA, the Project Organization for the Extension of the Maasvlakte, is a 50/50 joint venture between dredging and marine contractors Boskalis and Van Oord. The consortium has been contracted by the Rotterdam Port Authority to construct the first phase of the Maasvlakte 2 Project – the extension of the Port of Rotterdam – between 2008 and 2013. The new zone will encompass 2,000 hectares of new land, roughly the same size as the total surface area of Schiphol airport. Half of the area will become land for a future business park.

Gbaran_Ubie_filter_placement_header.jpg

Riverbed and slope protection, Gbaran Ubie

The Shell Petroleum Development Company of Nigeria Limited (SPDC) has constructed a gas processing facility in the Niger Delta on the outside bank of a bend of the River Nun at Gbaran Ubie, north of Yenagoa. To facilitate the importation of the processing modules, a Materials Offloading Quay was constructed, including a ro-ro ramp, a passenger jetty and a fire water station.