Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

FPSO Petrojarl Knarr

The Petrojarl Knarr is one of the world’s largest floating production and storage units (FPSO) for harsh environments. The FPSO is owned by Teekay, a market leader in FPSO solutions for companies that produce oil and gas in deep waters and harsh weather conditions, and it is the company’s largest project to date. Petrojarl Knarr, which was newly built by Samsung Heavy Industries in Geoje, South Korea, is 256.4 m long and 48 m wide with a deadweight of 135,000 tons. It has a production capacity of 63,000 barrels a day and a storage capacity of 800,000 barrels. The FPSO will operate on the Knarr oil and gas field in the Norwegian North Sea for BG Norge.

Project challenges

The main challenges, which were dealt with effectively during project preparation and execution, were: 

  • Weather: The typhoon season in the Northwestern Pacific starts at this time of year. In addition, the Cape of Good Hope was rounded during the local winter. Several weather agencies monitored the weather under way closely and forecasts were used as a basis for decisions by the experienced crew on board. 
  • Towage by three tugs: Well-documented and well-trained procedures were in place specifically for three-tug towage to prevent any unsafe situations during the tow.
  • Logistics: The various scheduled port calls were carefully planned and executed with assistance from local port agents to prevent unnecessary loss of time. 

Conclusion

The FPSO Petrojarl Knarr was towed effectively and safely, despite the distance and weather limitations along the route. With an average speed of 10.74 knots the three Fairmount tugs towed the FPSO more than 16,000 miles from South Korea to Norway in just 61 towing days, which is extremely fast, especially for an FPSO this size. Evaluating the project preparation and execution, it can be concluded that the operational best practices with the experienced crew on board were decisive for the safe, controlled and successful execution of this towage.

Related projects

Selected filters
005dd16062014Boskalis-_c_Kloet_header.jpg

Transport and installation depletion compression platform,
Malampaya phase 3

The Malampaya Deep Water Gas-to-Power Project is a joint venture involving the Philippine National Oil Company, Chevron and Shell Philippines Exploration. The project is part of the optimization of the Malampaya gas field which will lead to an eight-year lifetime extension.

SMIT_Subsea_Constructor-MaerskOil_Dan_56768_header.jpg

Platform reinforcement, DABRAT

Boskalis Offshore was awarded a contract by Maersk for the DABRAT project, involving both the preparation and construction work to the Dan A and Dan B offshore oil production facilities. The extensive scope not only included the subsea installation and removal work, but also fabrication of structural items, procurement, setting up and testing of lift equipment and structural examinations. The works covered the years 2013 and 2014.

Fairmount_Sherpa_assisted_by_local_harbor_tugs_towing_in_the_FPSO_at_Haugesund_header.jpg

Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

140718_-_48.jpg

Wintershall L8-P4

Wintershall Noordzee B.V. installed a new remote platform at L6-B as a gas production tie-back to L8-P4. L6-B is a remote and unmanned gas well unit. Utilising a dry-tree design, all control, power and metered injection for the two wells will be via the 19.5-km control umbilical between the new satellite platform L6-B and the operational gas platform L8-P4. 

DONG_Rockpiper_West_of_Duddon_Sands_header.jpg

Wind farm foundation installation, West of Duddon Sands

With 108 wind turbines producing almost 400 megawatts, West of Duddon Sands is one of the larger European wind farms. It is being built by a joint venture of Dong Energy and Scottish Power Renewables. Boskalis Offshore and Volker Stevin Offshore - in an Offshore WindForce joint venture - were responsible for the transport and installation of the 108 foundations for the wind farm.

Java-Bali_header.jpg

Submarine cables, Java-Bali

The island of Bali has been suffering a constant shortage of power. PLN contracted a Consortium of PT. Boskalis International Indonesia, Sumitomo Corporation and J-Power Systems Corporation to procure and install two 150 kV submarine and underground interconnecting power cables to replace existing cables and to reinforce the link between the electricity grids on the Indonesian islands of Java and Bali.