Tow-out and towage,
FPSO Petrojarl Knarr

Teekay awarded Fairmount Marine, a 100% subsidiary of Boskalis, a contract for the tow-out and towage of the FPSO from Geoje, South Korea to the port of Haugesund in Norway.

FPSO Petrojarl Knarr

The Petrojarl Knarr is one of the world’s largest floating production and storage units (FPSO) for harsh environments. The FPSO is owned by Teekay, a market leader in FPSO solutions for companies that produce oil and gas in deep waters and harsh weather conditions, and it is the company’s largest project to date. Petrojarl Knarr, which was newly built by Samsung Heavy Industries in Geoje, South Korea, is 256.4 m long and 48 m wide with a deadweight of 135,000 tons. It has a production capacity of 63,000 barrels a day and a storage capacity of 800,000 barrels. The FPSO will operate on the Knarr oil and gas field in the Norwegian North Sea for BG Norge.

Project challenges

The main challenges, which were dealt with effectively during project preparation and execution, were: 

  • Weather: The typhoon season in the Northwestern Pacific starts at this time of year. In addition, the Cape of Good Hope was rounded during the local winter. Several weather agencies monitored the weather under way closely and forecasts were used as a basis for decisions by the experienced crew on board. 
  • Towage by three tugs: Well-documented and well-trained procedures were in place specifically for three-tug towage to prevent any unsafe situations during the tow.
  • Logistics: The various scheduled port calls were carefully planned and executed with assistance from local port agents to prevent unnecessary loss of time. 

Conclusion

The FPSO Petrojarl Knarr was towed effectively and safely, despite the distance and weather limitations along the route. With an average speed of 10.74 knots the three Fairmount tugs towed the FPSO more than 16,000 miles from South Korea to Norway in just 61 towing days, which is extremely fast, especially for an FPSO this size. Evaluating the project preparation and execution, it can be concluded that the operational best practices with the experienced crew on board were decisive for the safe, controlled and successful execution of this towage.

Related projects

Selected filters
D1107-1233_header.jpg

Seabed preparatory works,
Dana Medway

Dana Petroleum Netherlands B.V. is the operator of the Pllb De Ruyter field and oil-producing platform located in the Dutch section of the North Sea.

DPFV_Sandpiper_accompagnied_by_SMIT_tugs_on_her_way__to_worksite_header.jpg

Rock installation, PDET

In 2008 Boskalis was approached by Petrobras to carry out a rock installation project at the oceanic terminal, one of Petrobras’ offshore oil production locations. The terminal, situated at Campos Basin offshore Rio de Janeiro, Brazil, is a maritime complex consisting of one Independent Re-pump Platform (PRA-1), two monobuoys and a FSO vessel which links to a 20 inch gas pipeline system.

Belwind_1_bewerkt_header.jpg

Construction wind farm, Belwind

SMIT sheerlegs Taklift 4 installed the final element for one of Belgium’s first offshore wind farms, Belwind, the wind farm’s high voltage transformer substation. SMIT also provided the transport of the element and other marine support services to assist the construction of the wind farm.

Walney_wind_farm_UK_support_installatie_monopiles_windmolens_header.jpg

Offshore wind farm, Walney

Windfarm construction projects regularly feature in the work programmes of SMIT’s sheerlegs fleet. For example, the Taklift 7 was involved in the Walney Offshore Windfarm development in the Irish Sea. Walney Offshore is a wind farm project developed by DONG in the Irish Sea, some 20 miles from the coast at Barrow.

Magellan_4_header.jpg

Pipeline crossing, Strait of Magellan

The project involved the construction of a new, strategically important, 24" natural gas pipeline across the Strait of Magellan, linking Cabo Espíritu Santo in Tierra del Fuego province with Cabo Vírgenes in Santa Cruz province. The new pipeline was built as an expansion of the existing San Martín pipeline in an effort by the government to increase gas supplies from Tierra del Fuego to the Argentinian mainland.

TR_Giant_4_header.jpg

Offshore wind farm, Sprogø

On behalf of marine contractor Aarsleff, SMIT was involved in the construction of the new Sprogø Offshore Windfarm, west of Copenhagen.